Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Works (Stage 2)

 

Environmental Permit no. EP-356/2009,

Further Evironmental permit nos. fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and Fep-05/356/2009

 

Monthly Environmental Monitoring & Audit Report

 

- October 2012 -


CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

13 November 2012


Table of contents

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 13

1.1        Scope of the Report 14

1.2        Structure of the Report 14

2.     Project Background. 16

2.1        Background. 16

2.2        Scope of the Project and Site Description. 16

2.3        Division of the Project Responsibility. 17

2.4        Project Organization and Contact Personnel 18

3.     Status of Regulatory Compliance. 26

3.1        Status of Environmental Licensing and Permitting under the Project 26

4.     Monitoring Requirements. 38

4.1        Noise Monitoring. 38

4.2        Air Monitoring. 39

4.3        Water Quality Monitoring. 42

5.     Monitoring Results. 47

5.1        Noise Monitoring Results. 47

5.2        Real-time Noise Monitoring. 49

5.3        Air Monitoring Results. 50

5.4        Water Monitoring Results. 51

5.5        Waste Monitoring Results. 57

6.     Compliance Audit. 60

6.1        Noise Monitoring. 61

6.2        Real-time noise Monitoring. 61

6.3        Air Monitoring. 61

6.4        Water Quality Monitoring. 61

6.5        Review of the Reasons for and the Implications of Non-compliance. 64

6.6        Summary of action taken in the event of and follow-up on non-compliance. 64

7.     Cumulative Construction Impact due to the Concurrent Projects. 65

8.     Environmental Site Audit. 66

9.     Complaints, Notification of Summons and Prosecution. 67

10.    Conclusion. 71


lIST OF TABLES

 

Table I         Summary of Water Quality Monitoring Exceedances in Reporting Month

Table II        Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Table 2.1     Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/11

Table 3.3      Summary of submission status under FEP-01/356/2009 Condition

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.5      Summary of submission status under FEP-02/356/2009 Condition

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.7      Summary of submission status under FEP-03/356/2009 Condition

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.9      Summary of submission status under FEP-04/356/2009 Condition

Table 3.10    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2010/06

Table 3.11    Summary of submission status under EP-356/2009 and FEP-05/356/2009 Condition

Table 3.12    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Table 4.1      Noise Monitoring Station

Table 4.2      Real Time Noise Monitoring Station

Table 4.3      Air Monitoring Station

Table 4.4     Marine Water Quality Stations for Water Quality Monitoring

Table 4.5      Marine Water Quality Monitoring Frequency and Parameters

Table 4.6     Marine Water Quality Stations for Enhanced Water Quality Monitoring

Table 4.7     Marine Water Quality Stations for Additional DO Monitoring

Table 5.1     Noise Monitoring Stations for Contract no. HY/2009/11

Table 5.2     Noise Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06

Table 5.3     Noise Monitoring Station for Contract no. HY/2009/15

Table 5.4     Noise Monitoring Station for Contract no. HY/2009/19

Table 5.5      Real Time Noise Monitoring Station for Contract no. HY/2009/11 and HY/2009/19

Table 5.6     Air Monitoring Stations for Contract no. HY/2009/11

Table 5.7     Air Monitoring Stations for Contract no. HK/2009/01

Table 5.8     Air Monitoring Station for Contract no. HK/2009/02

Table 5.9     Air Monitoring Station for Contract no. HY/2009/15

Table 5.10    Air Monitoring Stations for Contract no. HY/2009/19

Table 5.11    Water Monitoring Stations for Contract no. HY/2009/11

Table 5.12    Water Monitoring Stations for Contract no. HK/2009/01

Table 5.13    Water Monitoring Stations for Contract no. HK/2009/02

Table 5.14    Water Monitoring Stations for Contract no. HK/2010/06

Table 5.15    Water Monitoring Stations for Contract no. HY/2009/15

Table 5.16    Water Monitoring Stations for Contract no. HY/2009/19

Table 5.17    Summary of Water Quality Monitoring Exceedances in Reporting Month

Table 5.18    Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Table 5.19    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.20    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.21    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.22    Details of Waste Disposal for Contract no. HK/2010/06

Table 5.23    Details of Waste Disposal for Contract no. HY/2009/19

 

Table 8.1     Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.2     Summary of Environmental Inspections for Contract no. HK/2009/02

Table 8.3     Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.4     Summary of Environmental Inspections for Contract no. HK/2010/06

Table 8.5      Summary of Environmental Inspections for Contract no. HY/2009/19

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Construction Activities and Recommended Mitigation Measures in Coming Reporting Month

 

 

lIST OF FIGUREs

 

Figure 2.1       Project Layout

Figure 2.2       Project Organization Chart

Figure 2.3    Locations of Environmental Monitoring Stations

 

 

 

lIST OF APPENDIces

 

Appendix 3.1  Environmental Mitigation Implementation Schedule

Appendix 4.1  Action and Limit Level

Appendix 4.2  Copies of Calibration Certificates

Appendix 5.1  Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2  Noise Monitoring Results and Graphical Presentations

Appendix 5.3  Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4  Water Quality Monitoring Results and Graphical Presentations

Appendix 5.4a  Additional Dissolved Oxygen Monitoring Results

Appendix 5.5  Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1  Event Action Plans

Appendix 6.2  Summary for Notification of Exceedance

Appendix 7.1  Complaint Log

Appendix 8.1  Construction Programme of Individual Contracts


 

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report ¡VOctober 2012 for the Project of Wan Chai Development Phase II and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009. This report presents the environmental monitoring findings and information recorded during the period September 2012 to October 2012. The cut-off date of reporting is at 27th of each reporting month.

 

Construction Activities for the Reported Period

  1. Contract no. HY/2009/11- North Point Reclamation

¡P          The Contractor HY/2009/11 had been submitted the surrender of Further Environmental Permit (FEP-01/356/2009) to EPD on 24 October 2012

¡P          The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19.

 

  1. During this reporting period, the major work activities for Contract no. HK/2009/01 included:

Marine Works (at Wan Chai)

¡P          Rockfilling for HKCEC3E (East of HKCEC) between CH290 and CH385

¡P          Installation of pipe pile wall for demolition of existing seawall at Expo Drive East. Grouting works to pipe pile

¡P          Dredging works for Type 3 sediment beneath Expo Drive East bridge

¡P          Dredging works for Type 2 sediment beneath Expo Drive East bridge

¡P          Fabrication of 3 nos. of precast concrete caisson seawall, 1 no. precast concrete box culvert (namely Bay 100 and 2 nos. precast discharge outfall in precasting yard at Guangdong, China

 

Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works (at TST)

¡P          Rockfilling and rock protection to cross-harbour watermains

¡P          Thrust block construction for A18B18

¡P          Platform erection for crawler crane demobilization at TST landfall near Salisbury Garden. Demobilization of 80t crawler crane from the jack-up barge.

¡P          Pressure test for fresh watermains CHE and CHF

¡P          Pressure test for cross-harbour watermains CHA and CHB

 

Fresh Watermains, Cooling Watermains and Salt Watermains (On Land)

¡P          Mainlaying works at Zone B1-5A, B2-1, B3-1, B5-1(Switch Room), B5-3(Switch Room), A1-1, A1-2, A1-4, A2-3D, A3-2A, A3-4B, C1-10 and Run-out of Renaissance Hotel

¡P          Mainlaying works and subsequent reinstatement in Zone B4-3 and Zone B4-1A

¡P          Mainlaying works and subsequent reinstatement in Zone A2-2 and TTA Zone A2-3D

¡P          Pipe laying works at Heading No. H6c has been completed and the road reinstatement works at the jacking pit of Zone A1-3B and TTA Zone A1-4

¡P          Pipe laying works for heading No. H6a.

¡P          Excavation works at Heading No. H1

¡P          Mainlaying and chamber construction works at the traffic island near junction of Convention Avenue and Fenwick Pier Street

¡P          Mainlaying works at Expo Drive East in Zone C1-10

¡P          Final cleaning, CCTV inspection and pressure test for the 9 nos. cooling watermains

E&M

¡P          Electrical works in cooling water pumping stations P5

¡P          Cable works at Zone B1-5A, Zone B5-1(Switch Room) and B5-3(Switch Room) Power energization to L.V. switchboard for cooling water pumping stations P1, P3 and P4 by HEC

¡P          Power supply to cooling water pumping stations P1 and P4 from L.V. switchboard

¡P          Optical fiber cabling works from cooling water pumping stations P1, P3, P4 and P5 to relative stakeholders

 

  1. During this reporting period, the major work activities for Contract no. HK/2009/02 included:

¡P          Repairing of door hinge in the New Public Toile

¡P          Modification work of PTI at Expo Drive East.

¡P          Modification work of bus station at Expo Drive East near EVA

¡P          Reinstatement at Tonnochy Road  - Harbour Road junction

¡P          Modification work of P7, P8 and P9 Cooling water pumping station

¡P          Cooling mains installation at west of Gate 1 inside ex-pet garden

¡P          FS inspection of WSD Pumping Station

¡P          E&M works at WSD Salt Water Pumping Station

¡P          Modification work of EVA at WSD Pumping Station

¡P          Stripping formwork and application of cement mortar for the tie bolt holes inside salt water intake culvert Bay 19b ~ Bay 24

¡P          Concreting for box-out of access chamber at Bay19b

¡P          Concreting of the base slab at salt water intake culvert Bay 19a and steel fixing of the wall and top slab

¡P          Remedial work of wall and top slab of salt water intake A and B was completed

¡P          Concreting of base slab at salt water intake culvert jacking pit at WCR1

¡P          Welding for the 2nd layer waling at salt water intake culvert Bay 9 to Bay 11 at WCR1

¡P          Concreting of wall and top slab of Bay 8 in salt water intake landside cofferdam

¡P          Concreting of pile caps and wall together with top slab of Bay 6 in salt water intake landside cofferdam

¡P          Concreting of base slab of Bay 1 and Bay 2 in salt water intake seaside cofferdam

¡P          Cavity grouting between the HDPE Pipes B and Concrete Sleeve Pipes at TBM Jacking Pit

¡P          Breaking the extra cement grout at deformed area for removal of HDPE Pipe A from tunnel and the re-splicing work.

¡P          Laying HDPE pipe A and pipe B at temporary steel bridge

¡P          Vertical bend installation of HDPE pipe A & pipe B and connection to short pipe 

¡P          Concreting the wall and top slab of box culvert N1 Bay 1 on UU bridge

¡P          Concreting the Inspection Manhole IM-03 & IM-04 at box culvert N1 Bay 2 and desilting opening DO-01 & DO-02

¡P          Concreting the pile caps of Bay 4 and Bay 5 of box culvert N1, backfill the area with concrete outside the caps

 

  1. During this reporting period, the major work activities for Contract no. HY/2009/15 included:

¡P          TZ1 reclamation works

¡P          Formation of temporary seawall at TS2

¡P          Seawall trench works at TS2

 

  1. During this reporting period, the major work activities for Contract no. HK/2010/06 included:

¡P          Pile head breaking

¡P          Sonic tube trimming

 

  1. During this reporting period, the major work activities for Contract no. HY/2009/19 included:

¡P          Marine bored piling

¡P          Construction works for Box Culvert T

¡P          Construction of 1500f drainage pipe

 

 

Noise Monitoring

  1. Noise monitoring during daytime and restricted hour were conducted at the stations M1a, M2b, M3a, M4b, M5b and M6 on a weekly basis in the reporting month.
  2. One limit level exceedance was recorded at M6 on 16 October 2012. The limit level exceedance was considered as non-project related.

 

Real-time Noise Monitoring

  1. Real-time noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot and Oil Street Community Centre have been commenced on 5 October 2010 for the filling works of Contract no. HY/2009/11.
  2. Real-time noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot commenced external wall renovation since 1 June 2012
  3. The real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of noise sensitive receiver- City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.
  4. Exceedances were recorded between 2100 and 2130 hours on 1 Oct 2012 at FEHD Hong Kong Transport Section Whitefield Depot and Oil Street Community Centre throughout the reporting month.  Investigations found that the major noise impacts from 2100 to 2130 hours were arising from the display of pyrotechnics on 1 Oct 2012. In addition, there was no construction activity commenced in these two periods.  As such, the exceedances were concluded as not project related.

 

Air Quality Monitoring

  1. Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b ¡V Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.
  2. Due to lack of electricity supply, the 24-hr TSP monitoring at the following stations were rescheduled:

CMA2a: from 22 October 2012 to 24 October 2012

CMA4a: from 29 September 2012 to 3 October 2012

 

  1. Air quality monitoring has been conducted at stations CMA1b, CMA2a, CMA3a, CMA4a, CMA5a and CMA6a. No exceedance was recorded in the reporting month.

 

Water Quality Monitoring

  1. WDII/RSS advised that the dredging works for submarine pipeline at Victoria Harbour had been completed in January 2012. Therefore, the concurrent dredging activities at Sewage Pipeline Zone and reclamation shoreline zone TCBR under the EP-356/2009 scenario 2B no longer exist. As such, with reference to Table 5.39 of the EIA Report for Wan Chai Development Phase II and Central-Wan Chai Bypass, the application of silt screen for cooling water intakes for Queensway Government Offices was suspended and the others were remains unchanged.
  2. Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no water deterioration with respect to NPR was commenced since 7 Jan 2012 and was completed on 6 Feb 2012 water quality monitoring.
  3. Water quality monitoring at WSD10 and WSD15 will be temporary suspended while water quality monitoring at WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 12 onwards;
  4. Water quality monitoring at C8 and C9 have been implemented with respect to HY/2009/19 since the marine bore piling work started on 28 Jan 12.
  5. Based on the safety concern when external façade refurbishment was conducted by contractor employed by Provident Centre (C9) between 9 January 2012 to 30 July 2012 which caused to the inaccessibility of sampling either land and marine since 3 Feb 2012, there is a fine adjustment of the sampling location of water quality monitoring at C9 since 10 March 2012 to the closest accessible point prior to the completion of the external façade refurbishment work.
  6. Due to the access of water monitoring station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and marine, there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012 to the closest accessible point prior to the completion of the construction activities.
  7. Due to the dredging works for Cross Harbour Water Mains from Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April 2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for 4-week period after the completion of DP6 to confirm no water deterioration.
  8. As the removal of reclamation work of TS1 at CBTS has been completed, all procedures have been rectified and complied with the conditions set in EP-356/2009 and FEP-04/356/2009.
  9. Water quality monitoring at 14 monitoring stations was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table I.

Table I    Summary of Water Quality Monitoring Exceedances in Reporting Month

 

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HY/2009/11

WSD9

0

0

0

0

0

0

0

0

0

0

0

0

Monitoring finished on

6 Feb 2012

WSD10

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD15

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD17

0

0

0

0

0

0

0

0

0

0

0

0

 

C8

0

0

0

0

0

0

0

0

0

0

0

0

 

C9

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/01

WSD19

0

0

0

4

0

3

0

0

2

2

0

2

 

C1

1

0

0

0

0

0

0

0

0

0

0

0

 

C3

4

0

0

0

1

0

0

0

0

0

0

0

 

C4e

1

0

0

0

0

0

1

0

0

0

0

0

 

C4w

2

1

0

0

0

0

3

0

0

0

0

0

Monitoring finished on 27 April 2012

WSD20

0

0

0

0

0

0

0

0

0

0

0

0

WSD7

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/01

& HK/2010/06

C2

0

0

0

0

1

0

0

0

0

0

0

0

HK/2009/02

C5e

0

0

0

2

0

1

0

0

0

2

1

1

 

C5w

0

0

1

1

0

1

0

0

0

3

0

2

Monitoring started on

8 Feb 2012

WSD21

4

2

0

0

3

1

3

1

1

0

0

0

WSD9

0

0

0

0

1

0

0

0

0

0

0

0

 

WSD17

0

0

1

7

0

5

0

0

0

1

0

1

HY/2009/15

C7

1

1

0

0

0

0

2

0

0

0

0

0

HY/2009/19

Monitoring started on 28 Jan 2012

C8

0

0

3

4

1

0

0

0

1

1

0

0

C9

0

0

4

2

2

1

0

0

2

0

0

0

Total

13

4

9

20

9

12

9

1

6

9

1

6

 

Remarks: -    The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

         -   WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.

-   4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.

-   C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-   WSD7 and WSD20 water quality monitoring were temporarily suspended from 27 Apr 2012.

 

  1. Investigations were found that 6 turbidity and 5 SS exceedances which were Project-related to Contract no. HK/2009/02. The details of the recorded exceedances can be referred to the Section 6.4.

 

  1. Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table II.

      

Table II   Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

DO

AL

LL

AL

LL

HY/2009/15

C6

1

0

0

0

C7

3

2

1

1

Ex-WPCWA SW

1

8

1

9

Ex-WPCWA SE

4

6

3

7

Total

9

16

5

17

 

  1. There were 14 action level exceedances and 33 limit level exceedances of enhanced dissolved oxygen recorded in this reporting month. Investigation found that the exceedances are not related to the Project works. The details of the recorded exceedances can be referred to the Section 6.4.
  2. In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. There was no complaint received in this reporting month.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract nos. HK/2009/01, HK/2009/02, HY/2009/15 HK/2010/06 and HY/2009/19 under EP no. EP-356/2009 in the reporting month. Major observations and recommendations made during the audit sessions were rectified by the Contractors. No non-conformance was identified during the site inspections.

Future Key Issues

  1. In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/11- North Point Reclamation

¡P          The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

Marine Works

¡P          Fabrication of precast concrete caisson seawalls, precast box culvert (Bay 10) and precast discharge outfall in precasting yard at Guangdong, China and anticipated to be delivered to Site. Installation of the precast units

¡P          Dredging works for Type 2 sediment underneath Expo Drive East Bridge

¡P          Dredging works between CH290 and CH370 at east of HKCEC near Wan Chai west ferry pier

¡P          Grouting works and tie back system for construction of pipe pile wall near Expo Drive East. Removal of seawall at Expo Drive East

¡P          Rockfilling at east of HKCEC near Expo Drive East

¡P          Trust block construction at TST landfall

¡P          Rockfilling and rock armour protection works to cross-harbour watermains

¡P          Reinstatement works at TST seashore including removal of silt screen and demobilization of jack-up barge

¡P          Fresh water flushing, final cleaning and sterilizatioin for cross-harbour watermains CHA, CHB, CHE & CHF

¡P          Installation of Impressed Current Cathodic Protection (ICCP) system to CHA and CHB

Fresh Watermains, Cooling Watermains and Salt Watermains (On Land)

¡P          Works would be continued at Zone B1-5A, B2-1, B5-1(Switch Room), B5- 3(Switch Room), A1-1, A1-2, A2-2, A1-4(CHWM), A2-3D, A3-2A, A3-4B, run-out of Renaissance Hotel and C1-10

¡P          Mainlaying works at Zone C1-10 and run-out of Renaissance Hotel

¡P          Reinstatement works at Zone B1-5A and B2-1

¡P          Mainlaying works at Zone B3-1

¡P          Mainlaying works at Convention Avenue in Zone A1-1 and A1-2 and the next TTA workfront at Zone A1-2 (CHWM)

¡P          Mainlaying works and grouting works at jacking pit in Zone A1-3A & A1-4A of Convention Avenue would be resumed upon completion of pressure test for intake and discharge pipeline of SOC and HKAPA.

¡P          Mainlaying works at traffic island near junction between Convention Avenue and Fenwick Pier Street

¡P          Pipe laying works for Heading no. H1

¡P          Mainlaying works at Zone A3-4B and the works at Zone A3-4A & A3-5A would be subsequently commenced concurrently after the Zone A3-4B had been completed reinstated and reopened to public.

¡P          Pipe laying works for cross harbour watermains across HKCEC water channel

¡P          Pressure test for the 9 nos. cooling watermains

E&M Works

¡P          Electrical works in Cooling Water Pumping Stations P5

¡P          Initial commissioning for Cooling Water Pumping Stations P5

¡P          Major cabling works from existing LV Switch-board Room to Cooling Water Pumping Stations P5

¡P          Power energization for Cooling Water Pumping Stations P5

¡P          Full commissioning for Cooling Water Pumping Stations P1

¡P          Full commissioning for Cooling Water Pumping Stations P3, P4 & P5

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

¡P          Repairing of door hinge in the New Public Toile

¡P          Modification work of PTI at Expo Drive East.

¡P          Modification work of bus station at Expo Drive East near EVA

¡P          Reinstatement at Tonnochy Road  - Harbour Road junction

¡P          Modification work of P7, P8 and P9 Cooling water pumping station

¡P          Cooling mains installation at west of Gate 1 inside ex-pet garden

¡P          FS inspection of WSD Pumping Station

¡P          E&M works at WSD Salt Water Pumping Station

¡P          Modification work of EVA at WSD Pumping Station

¡P          Stripping formwork and application of cement mortar for the tie bolt holes inside salt water intake culvert Bay 19b ~ Bay 24

¡P          Concreting for box-out of access chamber at Bay19b

¡P          Concreting of the base slab at salt water intake culvert Bay 19a and steel fixing of the wall and top slab

¡P          Remedial work of wall and top slab of salt water intake A and B was completed

¡P          Concreting of base slab at salt water intake culvert jacking pit at WCR1

¡P          Welding for the 2nd layer waling at salt water intake culvert Bay 9 to Bay 11 at WCR1

¡P          Concreting of wall and top slab of Bay 8 in salt water intake landside cofferdam

¡P          Concreting of pile caps and wall together with top slab of Bay 6 in salt water intake landside cofferdam

¡P          Concreting of base slab of Bay 1 and Bay 2 in salt water intake seaside cofferdam

¡P          Cavity grouting between the HDPE Pipes B and Concrete Sleeve Pipes at TBM Jacking Pit

¡P          Breaking the extra cement grout at deformed area for removal of HDPE Pipe A from tunnel and the re-splicing work.

¡P          Laying HDPE pipe A and pipe B at temporary steel bridge

¡P          Vertical bend installation of HDPE pipe A & pipe B and connection to short pipe 

¡P          Concreting the wall and top slab of box culvert N1 Bay 1 on UU bridge

¡P          Concreting the Inspection Manhole IM-03 & IM-04 at box culvert N1 Bay 2 and desilting opening DO-01 & DO-02

¡P          Concreting the pile caps of Bay 4 and Bay 5 of box culvert N1, backfill the area with concrete outside the caps

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

¡P          TZ1 reclamation works

¡P          Dredging for seawall foundation at TS2

¡P          Seawall trench works at TS2

 

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line

¡P      Pile head breaking

¡P      Sonic tube trimming

 

Contract no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

¡P          Construction works for Box Culvert T

¡P          Marine Piling

¡P          Construction of 1500f drainage pipe

 

1.         Introduction

1.1               Scope of the Report

1.1.1.        Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.        This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under Particular Specification Section 27.

1.1.3.        This report documents the finding of EM&A works for Environmental Permit no. EP-356/2009, Further Environmental Permit no. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 and during the period of September to October. The cut-off date of reporting is at 27th of each reporting month.

 

1.2               Structure of the Report

 

Section 1        Introduction ¡V details the scope and structure of the report.

 

Section 2        Project Background ¡V summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3        Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4        Monitoring Requirements ¡V summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5        Monitoring Results ¡V summarizes the monitoring results obtained in the reporting period.

 

Section 6        Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7        Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8        Site Inspection ¡V summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9        Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10       Conclusion

2.         Project Background

2.1               Background

2.1.1.        ¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.        The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.        There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2               Scope of the Project and Site Description

2.2.1.        The Project is located mainly in Wan Chai North, Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road Interchange to the east, as shown in Figure 2.1.

2.2.2.        The study area encompasses existing developments along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers¡¦ Club, the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential developments.

2.2.3.        The scope of the Project comprises:

¡P          Land formation for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the development of an attractive waterfront promenade for the enjoyment of the public

¡P          Reprovisioning / protection of the existing facilities and structures affected by the land formation works mentioned above

¡P          Extension, modification, reprovisioning or protection of existing storm water drainage outfalls, sewerage outfalls and watermains affected by the revised land use and land formation works mentioned above

¡P          Upgrading of hinterland storm water drainage system and sewerage system, which would be rendered insufficient by the land formation works mentioned above

¡P          Provision of the ground level roads, flyovers, footbridges, necessary transport facilities and the associated utility services

¡P          Construction of the new waterfront promenade, landscape works and the associated utility services

¡P          The Trunk Road (i.e. CWB) within the study area and the associated slip roads for connection to the Trunk Road.

 

2.2.4.        The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1      Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3               Division of the Project Responsibility

2.3.1.        Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced. Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits (FEP) such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.        The details of individual contracts are summarized in Table 2.2.

 

 

 

Table 2.2 Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HK/2009/01

Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong Convention and Exhibition Centre

DP3, DP6

23 July 2010

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

DP3, DP5

5 July 2010

DP1

26 April 2011

HY/2009/11

Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North Point Reclamation

DP3

17 March 2010 (Under application

of surrender)

HY/2009/15

Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

DP3

10 November 2010

DP1

13 July 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

HY/2009/17

Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central - Wan Chai Bypass (CWB) ¡V Central Interchange

DP1

21 April 2011

HY/2009/19

Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

 

2.4               Project Organization and Contact Personnel

2.4.1.        Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.        The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3 Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer¡¦s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer¡¦s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3912 3388

3912 3010

China Harbour- CRBC Joint Venture

Contractor under Contract no. HY/2009/11

Project Director

Mr. Cho Yu Fun

3157 1086

3157 1085

Project Manager

Mr. Gregory Wong

3157 1086

Site Agent

Mr. Daniel Cheung

3157 1086

Environmental Officer

Mr. C. M. Wong

3157 1086

Chun Wo ¡V Leader Joint Venture

Contractor under Contract no. HK/2009/01

Project Director

Mr. PL Yue

2162 9909

2587 1878

Site Agent

Mr. Paul Yu

9456 9819

Deputy Site Agent

Mr Andy Yu

96484896

Construction Manager

Mr Terry Wong

9757 9846

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Jack Chu

9775 3008

Environmental Officer (Compliance Manager)

Mr. Andy Mak

9103 2370

Chun Wo ¡V CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Site Agent

Mr. Chan Sing Cho

3658 3002

2827 9996

Quality & Environmental Manager

Mr. C.P. Ho

9191 8856

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Chan Wai Hung

2823 7813

2865 5229

Site Manager

P J Fan

3557 6368

2566 2192

 

 

 

Contractor¡¦s Representative

Mr. David Lau

3557 6358

 

 

Head of Construction

Manager

Roger Cheung

3557 6371

 

 

Senior Construction Manager

Gene Cheung

3557 6395

 

 

Environmental Officer

Mr. Daniel Sin

3557 6347

Gammon

-Leader JV

Contractor under Contract no. HK/2010/06

Project Manager

Mr. Paul Lui

9095 7922

2529 2880

Site Agent

Mr. Keith Tse

2529 2068

Environmental Officer

Mr. Lee Wai Man

9481 6024

Chun Wo - CRGL - MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

 

Project Manager

Mr. Rayland Lee

3758 8879

2570 8013

 

Site Agent

Mr. Cheung Kit Cheung

6909 1555

Environmental Engineer

Mr. Calvin Leung

9286 9208

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Construction Manager (Marine)

William Luk

9610 1101

Construction Manager

(Land)

Patrick Cheung

9643 3012

Construction Manager

(Land)

Eric Fong

6191 9337

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3743 0788

3548 6988

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

 

2.4.3.        For Contract no. HY/2009/11, the principal work activities in this reporting month included:

¡P          The Contractor HY/2009/11 had been submitted the surrender of Further Environmental Permit (FEP-01/356/2009) to EPD on 24 October 2012

¡P          The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011.

 

2.4.4.        For Contract no. HK/2009/01, the principal work activities in this reporting month included:

Marine Works (at Wan Chai)

 

¡P          Rockfilling for HKCEC3E (East of HKCEC) between CH290 and CH385

¡P          Installation of pipe pile wall for demolition of existing seawall at Expo Drive East. Grouting works to pipe pile

¡P          Dredging works for Type 3 sediment beneath Expo Drive East bridge

¡P          Dredging works for Type 2 sediment beneath Expo Drive East bridge

¡P          Fabrication of 3 nos. of precast concrete caisson seawall, 1 no. precast concrete box culvert (namely Bay 100 and 2 nos. precast discharge outfall in precasting yard at Guangdong, China

Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works (at TST)

 

¡P          Rockfilling and rock protection to cross-harbour watermains

¡P          Thrust block construction for A18B18

¡P          Platform erection for crawler crane demobilization at TST landfall near Salisbury Garden. Demobilization of 80t crawler crane from the jack-up barge.

¡P          Pressure test for fresh watermains CHE and CHF

¡P          Pressure test for cross-harbour watermains CHA and CHB

 

Fresh Watermains, Cooling Watermains and Salt Watermains (On Land)

¡P          Mainlaying works at Zone B1-5A, B2-1, B3-1, B5-1(Switch Room), B5-3(Switch Room), A1-1, A1-2, A1-4, A2-3D, A3-2A, A3-4B, C1-10 and Run-out of Renaissance Hotel were in progress.

¡P          Mainlaying works and subsequent reinstatement in Zone B4-3 and Zone B4-1A were substantially completed.

¡P          Mainlaying works and subsequent reinstatement in Zone A2-2 was substantially completed and subsequent TTA Zone A2-3D was commenced.

¡P          Pipe laying works at Heading No. H6c has been completed and the road reinstatement works at the jacking pit of Zone A1-3B was completed. The subsequent TTA Zone A1-4 was commenced.

¡P          Pipe laying works for heading No. H6a was substantially completed.

¡P          Excavation works at Heading No. H1 was substantially completed.

¡P          Mainlaying and chamber construction works at the traffic island near junction of Convention Avenue and Fenwick Pier Street was currently in progress.

¡P          Mainlaying works at Expo Drive East in Zone C1-10 was in progress.

¡P          Final cleaning, CCTV inspection and pressure test for the 9 nos. cooling watermains was commenced.

E&M

¡P          Electrical works in cooling water pumping stations P5

¡P          Cable works at Zone B1-5A, Zone B5-1(Switch Room) and B5-3(Switch Room) Power energization to L.V. switchboard for cooling water pumping stations P1, P3 and P4 by HEC

¡P          Power supply to cooling water pumping stations P1 and P4 from L.V. switchboard

¡P          Optical fiber cabling works from cooling water pumping stations P1, P3, P4 and P5 to relative stakeholders

 

2.4.5.        For Contract no. HK/2009/02, the principal work activities in this reporting month included:

¡P          Repairing of door hinge in the New Public Toile

¡P          Modification work of PTI at Expo Drive East.

¡P          Modification work of bus station at Expo Drive East near EVA

¡P          Reinstatement at Tonnochy Road  - Harbour Road junction

¡P          Modification work of P7, P8 and P9 Cooling water pumping station

¡P          Cooling mains installation at west of Gate 1 inside ex-pet garden

¡P          FS inspection of WSD Pumping Station

¡P          E&M works at WSD Salt Water Pumping Station

¡P          Modification work of EVA at WSD Pumping Station

¡P          Stripping formwork and application of cement mortar for the tie bolt holes inside salt water intake culvert Bay 19b ~ Bay 24

¡P          Concreting for box-out of access chamber at Bay19b

¡P          Concreting of the base slab at salt water intake culvert Bay 19a and steel fixing of the wall and top slab

¡P          Remedial work of wall and top slab of salt water intake A and B was completed

¡P          Concreting of base slab at salt water intake culvert jacking pit at WCR1

¡P          Welding for the 2nd layer waling at salt water intake culvert Bay 9 to Bay 11 at WCR1

¡P          Concreting of wall and top slab of Bay 8 in salt water intake landside cofferdam

¡P          Concreting of pile caps and wall together with top slab of Bay 6 in salt water intake landside cofferdam

¡P          Concreting of base slab of Bay 1 and Bay 2 in salt water intake seaside cofferdam

¡P          Cavity grouting between the HDPE Pipes B and Concrete Sleeve Pipes at TBM Jacking Pit

¡P          Breaking the extra cement grout at deformed area for removal of HDPE Pipe A from tunnel and the re-splicing work.

¡P          Laying HDPE pipe A and pipe B at temporary steel bridge

¡P          Vertical bend installation of HDPE pipe A & pipe B and connection to short pipe 

¡P          Concreting the wall and top slab of box culvert N1 Bay 1 on UU bridge

¡P          Concreting the Inspection Manhole IM-03 & IM-04 at box culvert N1 Bay 2 and desilting opening DO-01 & DO-02

¡P          Concreting the pile caps of Bay 4 and Bay 5 of box culvert N1, backfill the area with concrete outside the caps

 

2.4.6.        For Contract no. HY/2009/15, the principal work activities in this reporting month included:

¡P          TZ1 reclamation works

¡P          Dredging for seawall foundation at TS2

¡P          Seawall trench works at TS2

2.4.7.        For Contract no. HK/2010/06, the principal work activities in this reporting month included:

¡P          Pile head breaking

¡P          Sonic tube trimming

2.4.8.        For Contract no. HY/2009/19, the principal work activity in this reporting month included:

¡P          Marine bored piling

¡P          Construction works for Box Culvert T

¡P          Construction of 1500f drainage pipe

 

2.4.9.        In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

Contract no. HY/2009/11- North Point Reclamation

¡P          The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

Marine Works

¡P          Fabrication of precast concrete caisson seawalls, precast box culvert (Bay 10) and precast discharge outfall in precasting yard at Guangdong, China and anticipated to be delivered to Site. Installation of the precast units

¡P          Dredging works for Type 2 sediment underneath Expo Drive East Bridge

¡P          Dredging works between CH290 and CH370 at east of HKCEC near Wan Chai west ferry pier

¡P          Grouting works and tie back system for construction of pipe pile wall near Expo Drive East. Removal of seawall at Expo Drive East

¡P          Rockfilling at east of HKCEC near Expo Drive East

¡P          Trust block construction at TST landfall

¡P          Rockfilling and rock armour protection works to cross-harbour watermains

¡P          Reinstatement works at TST seashore including removal of silt screen and demobilization of jack-up barge

¡P          Fresh water flushing, final cleaning and sterilizatioin for cross-harbour watermains CHA, CHB, CHE & CHF

¡P          Installation of Impressed Current Cathodic Protection (ICCP) system to CHA and CHB

 

Fresh Watermains, Cooling Watermains and Salt Watermains (On Land)

 

¡P          Works would be continued at Zone B1-5A, B2-1, B5-1(Switch Room), B5- 3(Switch Room), A1-1, A1-2, A2-2, A1-4(CHWM), A2-3D, A3-2A, A3-4B, run-out of Renaissance Hotel and C1-10

¡P          Mainlaying works at Zone C1-10 and run-out of Renaissance Hotel

¡P          Reinstatement works at Zone B1-5A and B2-1

¡P          Mainlaying works at Zone B3-1

¡P          Mainlaying works at Convention Avenue in Zone A1-1 and A1-2 and the next TTA workfront at Zone A1-2 (CHWM)

¡P          Mainlaying works and grouting works at jacking pit in Zone A1-3A & A1-4A of Convention Avenue would be resumed upon completion of pressure test for intake and discharge pipeline of SOC and HKAPA.

¡P          Mainlaying works at traffic island near junction between Convention Avenue and Fenwick Pier Street

¡P          Pipe laying works for Heading no. H1

¡P          Mainlaying works at Zone A3-4B and the works at Zone A3-4A & A3-5A would be subsequently commenced concurrently after the Zone A3-4B had been completed reinstated and reopened to public.

¡P          Pipe laying works for cross harbour watermains across HKCEC water channel

¡P          Pressure test for the 9 nos. cooling watermains

E&M Works

¡P          Electrical works in Cooling Water Pumping Stations P5

¡P          Initial commissioning for Cooling Water Pumping Stations P5

¡P          Major cabling works from existing LV Switch-board Room to Cooling Water Pumping Stations P5

¡P          Power energization for Cooling Water Pumping Stations P5

¡P          Full commissioning for Cooling Water Pumping Stations P1

¡P          Full commissioning for Cooling Water Pumping Stations P3, P4 & P5

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

¡P          Complete PTI modification works after completion of New Public Toilet in East Island at Expo Drive East.

¡P          Complete all cooling mains and cabling works for P7, P8 & P9 Pumping Stations permanent power-on and signal control.

¡P          Continue 800MS pipe installation inside Ex-pet Garden.

¡P          Complete modification work of EVA & Vehicle access at WSD Pumping Station

¡P          Complete the finishing works of WSD Salt Water Pumping Station.

¡P          Continue construction of Bay 1b ¡V 2, Bay 6 ¡V 8 salt water intake culverts at WCR1 area.

¡P          Complete ELS of the salt water intake culverts Bay 9 ¡V 11 to formation level at WCR1 area and commence culvert works.

¡P          Continue salt water intake culvert at transition bays inside jacking pit and receiving pit.

¡P          Continue remaining drainage works and reinstatement works along Wan Shing Street.

¡P          Complete HDPE piping inside outfall seaside cofferdam.

¡P          Continue construction for Box Culvert N1 at WCR1 area.

¡P          Continue concreting works for the Mezzanine Level at the New Ferry Pier.

¡P          Commence seawall strengthening works at WCR2 area.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

¡P          Formation of temporary seawall at TS2

¡P          TZ1 and TS2 reclamation works

 

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line

¡P          Pile head breaking

¡P          Platform Disassembly

¡P          Sonic tube trimming

¡P          Dredging

 

Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

¡P          Construction works for Box Culvert T

¡P          Marine Piling

¡P          Construction of 1500f drainage pipe

 

 

3.         Status of Regulatory Compliance

3.1               Status of Environmental Licensing and Permitting under the Project

 

3.1.1.        A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1 Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009/A

4 Aug 2010

Superseded

Environmental Permit

EP-364/2009/B

17 Aug 2009

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Under application of surrender

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 Jul 2010

Valid

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Valid

Further Environmental Permit

FEP-08/364/2009/A

15 Jun 2012

Valid

 

3.1.2.        Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

3.1.3.        The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011.

3.1.4.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and Table 3.3.

3.1.5.        Contractor submitted a letter dated 20 July 2011 to confirm that the dredging works and dumping operation were completed.

3.1.6.        The Contractor HY/2009/11 had been submitted the surrender of Further Environmental Permit (FEP-01/356/2009) to EPD on 24 October 2012

Table 3.2 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/11

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

N/A

Valid

Notification of Works Under APCO

331892

4 Jul. 2011

N/A

Valid

Registration as a Chemical Waste Producer

WPN5213-151-C3631-02

12 Oct 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7010037

13 Jan 2010

N/A

Valid

Discharge Licence

WT00007942-2010

29 Nov 2010

30 Nov 2015

Valid

 

Table 3.3 Summary of submission status under FEP-01/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

18 Dec 2009

Condition 2.7

Submission of works schedule and location plan

8 Feb 2010

Condition 2.8

Revised Silt Curtain Deployment Plan (Rev. 3)

4 Dec 2010

Condition 2.9

Silt Screen Deployment Plan (Rev. 6)

18 May 2011

Condition 2.10

Coral Translocation Plan

20 Nov 2009

Condition 2.16

Revised Noise Management Plan (Rev 5)

19 Feb 2011

Condition 2.17

Landscape Plan

12 May 2010

 

Revised landscape Plan

30 Jun 2010

 

Submission of Supplementary Information - Revised Management & Maintenance Schedule for Submitted Revised Landscape Plan

25 Aug 2010

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

3.1.7.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and Table 3.5.

Table 3.4 Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088      

6 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RE0174-12

5 Mar 2012

30 Mar 2012 to  29 Sep 2012

Expired

 

GW-RS0356-12

03 Apr 2012

11 Apr 2012   to 29 Sep 2012

Expired

 

GW-RS0394-12

16 Apr 2012

19 Apr 2012   to   12 Oct 2012

Expired

 

GW-RS0460-12

10 May 2012

13 May 2012 to 6 Nov 2012

Valid

 

GW-RS0514-12

14 May 2012

27 May 2012 to 26 Nov 2012

Valid

 

GW-RS0855-12

16 Aug 2012

17 Aug 2012 to  9 Feb 2013

Valid

 

GW-RS0862-12

20 Aug 2012

28 Aug 2012 to 27 Feb 2013

Valid

 

GW-RS0949-12

12 Sep 2012

16 Sep 2012 to 15 Mar 2013

Valid

 

 

GW-RS0545-12

24 May 2012

26 May 2012 to 25 Nov 2012

Valid

GW-RS0546-12

25 May 2012

26 May 2012 to 25 Nov 2012

Valid

GW-RS0760-12

18 Jul 2012

20 Jul 2012 to 19 Jan 2013

Valid

GW-RS0806-12

3 Aug 2012

4 Aug 2012 to 03 Feb 2013

Valid

GW-RS0823-12

3 Aug 2012

3 Aug 2012 to  02 Feb 2013

Valid

GW-RS0852-12

16 Aug 2012

16 Aug 2012 to 01 Feb 2013

Valid

GW-RS0994-12

25 Sep 2012

25 Sep 2012 to 19 Nov 2012

Valid

 

GW-RS1011-12

26 Sep 2012

30 Sep 2012 to 29 Mar 2013

Valid

 

GW-RS1017-12

27 Sep 2012

30 Sep 2012 to 24 Mar 2013

Valid

GW-RE0793-12

21 Sep 2012

30 Sep 2012 to 29 Mar 2013

Valid

GW-RS1040-12

8 Oct 2012

13 Oct 2012 to 12 Apr 2013

Valid

Discharge Licence

 

WT00006220-2010

18 Mar 2010

31 Mar 2015

Valid

WT00009641-2011

24 Jul 2011

31 Jul 2016

Valid

Billing account under Waste Disposal Ordinance

7010069

21 Jan 2010

N/A

 

Valid

Registration as a Chemical Waste Producer

WPN5213-134-C3585-01

21 Jan 2010

N/A

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/13-004

23 May 2012

24 May 2012 to 23 Nov 2012

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal)

EP/MD/13-062

9 Oct 2012

10 Oct 2012 to 9 Nov 2012

Valid

Permit for Dumping at Sea - Dredged Sediment Requiring Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers

EP/MD/13-061

4 Sep 2012

17 Sep 2012 to 16 Oct 2012

Expired

 

Table 3.5 Summary of submission status under FEP-02/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

13 Apr 2010

Condition 2.7

Works Schedule and Location Plan

8 Apr 2010

Condition 2.8

Silt Curtain Deployment Plan (Rev. 5)

24 Aug 2012

Silt Curtain Deployment Plan (Rev. 4)

12 July 2012

Condition 2.9

Silt Screen Deployment Plan

19 Apr 2010

Conditions 2.8 and 2.9

Supplementary Document on Silt Curtain and Silt Screen Deployment Plan

19 Jul 2010

Report on Field Testing for Silt Curtain

26 Aug 2010

Report on Field Testing for Silt Curtain (Rev. A)

15 Nov 2010

Condition 2.12(d)

Alternative Proposal on Concurrent Dredging for Sewage Pipeline and Cross Harbour Water Mains

15 Apr 2011

Condition 2.17

Noise Management Plan

23 Apr 2010

Condition 2.18

Landscape Plan (Erection of Decorative Screen Hoarding along Construction Site around Hong Kong Exhibition and Convention Centre)

15 May 2010

 

Landscape Plan (Night-time Lighting)

22 Oct 2010

 

Landscape Plan (Rev. B)

15 Nov 2010

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

3.1.8.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2009/02 under FEP-03/356/2009 are shown in Table 3.6 and Table 3.7.

Table 3.6 Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

N/A

Valid

 

FEP-01/364/2009

24 Mar 2010

N/A

Valid

Notification of Works Under APCO

313962

2 Feb 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0671-12

25 June 2012

17 Jul 2012 to 16 Jan 2013

Valid

 

GW-RS0730-12

9 July 2012

10 Jul 2012 to 8 Jan 2013

Valid

 

GW-RS0736-12

9 July 2012

9 Jul 2012 to   8 Jan 2013

Valid

 

GW-RE0283-12

5 Apr 2012

1 May 2012 to

30 Nov 2012

Valid

 

GW-RS0739-12

9 July 2012

1 Aug 2012 to 31 Jan 2013

Valid

 

GW-RS1038-12

10 Oct 2012

10 Oct 2012 to 9 Apr 2013

Valid

 

GW-RS1069-12

17 Oct 2012

19 Oct 2012 to 18 Apr 2013

Valid

 

GW-RS0341-12

3 Apr 2012

28 Apr 2012 to 27 Oct 2012

Valid

 

GW-RS0348-12

3 Apr 2012

10 Apr 2012 to 9 Oct 2012

Expired

 

GW-RS0380-12

12 Apr 2012

1 May 2012 to 31 Oct 2012

Valid

 

GW-RS0388-12

13 Apr 2012

1 May 2012 to 31 Oct 2012

Valid

 

GW-RS0418-12

30 Apr 2012

23 May 2012 to 22 Nov 2012

Valid

 

GW-RS0420-12

30 Apr 2012

18 May 2012 to 17 Nov 2012

Cancelled

 

GW-RS0423-12

30 Apr 2012

19 May 2012 to 18 Nov 2012

Cancelled

 

GW-RS0427-12

30 Apr 2012

23 May 2012 to 22 Nov 2012

Valid

GW-RS0533-12

21 May 2012

21 May 2012 to 10 Nov 2012

Valid

GW-RS0550-12

25 May 2012

7 June 2012 to 6 Dec 2012

Valid

GW-RS0611-12

14 June 2012

15 Jun 2012 to 28 Nov 2012

Valid

GW-RS0633-12

13 June 2012

16 Jun 2012 to 14 Dec 2012

Valid

GW-RS0814-12

3 Aug 2012

6 Aug 2012 to 5 Dec 2012

Valid

GW-RS0850-12

10 Aug 2012

14 Aug 2012 to 13 Feb 2013

Valid

GW-RS0870-12

21 Aug 2012

16 Sept 2012 to 31 Dec 2012

Valid

GW-RS0996-12

25 Sept 2012

26 Sept 2012 to 25 Mar 2013

Valid

Discharge Licence

 

WT00006249-2010

22 Mar 2010

31 Mar 2015

Valid

 

 

WT00006436-2010

15 Apr 2010

30 Apr 2015

Valid

WT00006673-2010

14 May 2010

31 Mar 2015

Cancelled

WT00006757-2010

28 May 2010

31 May 2015

Valid

WT00007129-2010

28 July 2010

31 Jul 2015

Valid

WT00008982-2011

26 April 2011

30 April 2016

Valid

WT00009691-2011

1 Aug 2011

31 July 2016

Valid

Billing Account under Waste Disposal Ordinance (Land)

7010255

10 Feb 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance (Marine)

7011496

6 Oct 2010

N/A

Valid

Registration as Chemical Waste Producer (Wan Chai)

WPN5213-135-C3593-01

10 Mar 2010

N/A

Valid

Registration as Chemical Waste Producer (TKO 137)

WPN5213-839-C3593-02

22 Sep 2010

N/A

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/13015

25 May 2012

29 May 2012 to 28 Nov 2012

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine disposal)

EP/MD/13-077

28 Sept 2012

6 Oct 2012 to 5 Nov 2012

Valid

 

EP/MD/13-058

29 Aug 2012

6 Sep 2012 to 5 Oct 2012

Expired

 

 

Table 3.7 Summary of submission status under FEP-03/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 1.12

Commencement Date of Construction of Marine Works

8 April 2010

Condition 2.6

Management Organization of Main Construction Companies

10 April 2010

Condition 2.7

Works Schedule and Location Plans

8 April 2010

Condition 2.8

Silt Curtain Deployment Plan (Revision A)

20 April 2010

Silt Curtain Deployment Plan (Revision B)

25 May 2010

Silt Curtain Deployment Plan (Revision C)

14 Jun 2010

Silt Curtain Deployment Plan (Revision H)

15 Feb 2011

Silt Curtain Deployment Plan (Revision I)

17 Nov 2011

Silt Curtain Deployment Plan (Revision J)

15 Feb 2012

Silt Curtain Deployment Plan (Revision K)

3 May 2012

Silt Curtain Deployment Plan (Revision L)

25 Oct 2012

Condition 2.9

 

 

Silt Screen Deployment Plan

21 April 2010

Supplementary Information for Existing WSD Salt Water Intakes at Quarry Bay and Sai Wan Ho

5 Oct 2010

Silt Screen Deployment Plan (Revision B)

15 Feb 2012

Silt Screen Deployment Plan (Revision C)

3 May 2012

Condition 2.17

Noise Management Plan

6 May 2010

Condition 2.18

Landscape Plan (Decorative Screen Hoarding)

11 May 2010

Landscape Plan (Control of Night Time Lighting)

2 June 2010

Landscape Plan (Combined Version)

20 July 2011

Landscape Plan (Combined Version)

5 Aug 2011

-----

Acknowledge of Submission

22 Aug 2011

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

3.1.9.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HY/2009/15 under EP-356/2009 are shown in Table 3.8 and Table 3.9.

Table 3.8 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

N/A

Valid

FEP-06/364/2009/A

22 Nov 2010

N/A

Valid

FEP-01/416/2011

11 Nov 2011

N/A

Valid

Notification of Works Under APCO

321822

24 Sep 2010

N/A

Valid

Construction Noise Permit (CNP) for Filling and Diaphragm Wall Works at TS4/ME4

GW-RS0924-12

31 Aug 2012

01 Sep 2012 to

28 Feb 2013

Valid

Construction Noise Permit (CNP) for bored pile construction at Eastern Breakwater of CBTS

GW-RS1009-12

03 Oct 2012

03 Oct 2012 to

25 Mar 2013

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0343-12

12 Apr 2012

13 Apr 2012 to

8 Oct 2012

Expired

Construction Noise Permit (CNP) for Removal Works at TS1

GW-RS0607-12

12 Jun 2012

13 Jun 2012 to

7 Dec 2012

Valid

Construction Noise Permit (CNP) for Dredging at TS2

GW-RS1023-12

05 Oct 2012

09 Oct 2012 to

25 Mar 2013

Valid

Registration as a Chemical Waste Producer

WPN5213-147-C1169-35

15 Nov 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7011553

30 Sep 2010

27 Sep 2010 to 27 Jan 2016

Valid

Billing Account under Waste Disposal Ordinance (Dumping by Vessel)

7011761

03 Oct 2012

17 Oct 2012  to

16 Jan 2013

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/13-018

6 Jun 2012

6 Jun 2012 to

5 Dec 2012

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine disposal)

EP/MD/13-076

28 Sep 2012

8 Oct 2012 to

7 Nov  2012

Valid

EP/MD/13-059

31 Aug 2012

8 Sep 2012 to

7 Oct  2012

Expired

 

Table 3.9 Summary of submission status under FEP-04/356/2009 Condition

 

FEP Condition

Submission

Date of Submission

Condition 2.7

Works Schedule and Location Plans

27 Oct 2010

 

Amendment for Works Schedule and Location Plans

12 Nov 2010

Condition 2.8

Silt Curtain Deployment Plan

30 Nov 2010

 

Amendment for Silt Curtain Deployment Plan

24 Feb 2011

Amendment for Silt Curtain Deployment Plan

11 May 2011

Amendment for Silt Curtain Deployment Plan

11 Sep 2012

Amendment for Silt Curtain Deployment Plan

30 Oct 2012

Condition 2.9

Silt Screen Deployment Plan

19 Oct 2010

Amendment for Silt Screen Deployment Plan

18 Feb 2011

Amendment for Silt Screen Deployment Plan

15 Jun 2011

Condition 2.18

Proposal for the Removal of Odorous Sediment and Slime

13 Jan 2011

Amendment for Proposal for the Removal of Odorous Sediment and Slime

8 Mar 2011

 

Amendment for Proposal for the Removal of Odorous Sediment and Slime

2 Aug 2011

Condition 2.21

Landscape Plan

18 Feb 2011

Condition 2.23

Noise Management Plan

20 Oct 2010

Amendment for Noise Management Plan

27 Jan 2011

 

3.1.10.    Implementation status of the recommended mitigation measures during this reporting period is presented in Appendix 3.1.

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line

3.1.11.    Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2010/06 under EP-356/2009 are shown in Table 3.10 and Table 3.11.

Table 3.10     Cumulative Summary of Valid Licences and Permits under Contract no. HK/2010/06

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

N/A

Valid

FEP-08/364//2009/A

15 June 2012

N/A

Valid

Notification of Works Under APCO

326344

18 Jan 2011

N/A

Valid

Construction Noise Permit (CNP) for piling equipment

PP-RS0012-12

18 June 2012

6 Jul 2012 to 5 Jan 2013

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0989-12

21 Sept 2012

6 Oct 2012 to 5 Apr 2013

Valid

GW-RS0313-12

27 Mar 2012

6 Apr to 5 Oct 2012

Expired

GW-RS0658-12

21 June 2012

13 Jul 2012 to 12 Jan 2013

Valid

GW-RS0923-12

31 Aug 2012

15 Oct 2012 to 15 Apr 2013

Valid

Billing Account under Waste Disposal Ordinance

7012338

16 Feb 2011

N/A

Valid

Registration as Chemical Waste Producer

WPN5213-134-G2533-01

11 Feb 2011

N/A

Valid

Water Discharge Licence

WT00010905-2011

4 November 2011

31 July 2016

Valid`

 

 

Table 3.11     Summary of submission status under EP-356/2009 and FEP-05/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

24 October 2011

Condition 2.7

Works Schedule and Location Plans

11 March 2011

Condition 2.8

Revised Silt Curtain Deployment Plan

31 Aug 2011

Revised Silt Curtain Deployment Plan

22 Oct 2012

Condition 2.9

Silt Screen Deployment Plan

11 April 2011

Condition 2.23

Noise Management Plan

11 March 2011

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

3.1.12.    Summary of the current status on licences and/or permits on environmental protection pertinent for contract no. HY/2009/19 is shown in Table 3.12.

Table 3.12     Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Permit / Licence / Notification / Approval

Reference No.

Issued Date

Valid Period / Expiry date

Status

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Granted

Valid

Notification of Works Under APCO

326160

24 Jan 2011

Notified

Valid

Construction Noise Permit (CNP) (For D-wall construction) (Portion I, VII, VIII & IX)

GW-RS0871-12

 

27-Aug-12

26-Feb-13

Valid

Construction Noise Permit (CNP) (For Bored pile construction at Portion III)

GW-RS0507-12

22-May-12

23-Nov-12

Cancelled

Construction Noise Permit (CNP) (For Bored pile construction at Portion III, V)

GW-RS0885-12

27-Aug-12

26-Feb-13

Valid

Construction Noise Permit (CNP) (For Watson Road)

GW-RS0589-12

18-Jun-12

17-Dec-12

Valid

Construction Noise Permit (CNP) (For IEC)

GW-RS0953-12

17-Sep-12

20-Mar-13

Valid

Construction Noise Permit (CNP) (For IEC Parapet Removal ¡V Loading/Unloading)

GW-RS1065-12

16-Oct-12

20-Apr-13

Valid

Discharge Licence (Land)

WT00010093-2011

 

17 Aug 2012

30-Sept-16

Valid

Discharge Licence (Sea)

WT00010865-2011

03 Nov 2011

30-Nov-16

Valid

Registration as a Waste Producer

7012306

21 Jan 2011

Registered

-

C&D Waste Disposal

7012306

10 Feb 2011

Registered

-

Vessel Disposal

7013285

21 July 2011

Registered

-

Registration as Chemical Waste Producer

5213-151-C3654-01

24 Mar 2011

Registered

-

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/12-150

14-May-12

14-Nov-12

Valid

Dumping Permit (Type 2 ¡V Confined Marine Disposal)

EP/MD/13-063

17 Sep 2012

16 Oct 2012

Expired

 

 

 


4.         Monitoring Requirements

4.1               Noise Monitoring

Noise Monitoring Stations

4.1.1.        The noise monitoring stations for the Project are listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.1 Noise Monitoring Station

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

Real-time Noise Monitoring Stations

4.1.2.        The real-time noise monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

4.1.3.        The real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of noise sensitive receiver- City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.

Table 4.2 Real Time Noise Monitoring Station

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitefield Depot

North Point

RTN2

Oil Street Community Liaison Centre

North Point

RTN2a

Electric Centre

 

Noise Monitoring Parameters, Frequency and Duration

4.1.4.        The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

4.1.5.        Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

¡P          one set of measurements between 0700 and 1900 hours on normal weekdays.

4.1.6.        If construction works are extended to include works during the hours of 1900 ¡V 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

Monitoring Equipment

4.1.7.        As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.1.8.        Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

 

4.2               Air Monitoring

Air Quality Monitoring Stations

4.2.1.        The air monitoring stations for the Project are listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.3 Air Monitoring Station

Station ID

Monitoring Location

Description

CMA1b

Oil Street Community Liaison Centre

North Point

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office *

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

Wan Chai

CMA6a

WDII PRE Site Office *

Wan Chai

* Remarks: As per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future CWB site office at Wanchai Waterfront Promenade and CMA6a - Future AECOM site office at Work Area were renamed as remark.

 

 

Air Monitoring Parameters, Frequency and Duration

4.2.2.        One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

4.2.3.        All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

4.2.4.        For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

4.2.5.        High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

¡P          0.6 - 1.7 m3 per minute adjustable flow range;

¡P          equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

¡P          installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

¡P          capable of providing a minimum exposed area of 406 cm2;

¡P          flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

¡P          equipped with a shelter to protect the filter and sampler;

¡P          incorporated with an electronic mass flow rate controller or other equivalent devices;

¡P          equipped with a flow recorder for continuous monitoring;

¡P          provided with a peaked roof inlet;

¡P          incorporated with a manometer;

¡P          able to hold and seal the filter paper to the sampler housing at horizontal position;

¡P          easily changeable filter; and

¡P          capable of operating continuously for a 24-hour period.

 

4.2.6.        Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

Laboratory Measurement / Analysis

4.2.7.        A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

4.2.8.        An alternative non-HOKLAS accredited laboratory was set-up for carrying out the laboratory analysis, the laboratory equipment was approved by the ER on 8 February 2011 and the measurement procedures were witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall regularly audit to the measurement performed by the laboratory to ensure the accuracy of measurement results.

4.2.9.        Filter paper of size 8" x 10" shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

4.2.10.    After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

4.2.11.    All the collected samples shall be kept in a good condition for 6 months before disposal.

impact monitoring for odour patrol

4.2.12.    Odour patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working Area when there is temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when there is dredging of the odorous sediment and slime at the south-western corner of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at bi-weekly intervals during July, August and September by a qualified person of the ET who shall:

¡P          be at least 16 years of age;

¡P          be free from any respiratory illnesses; and

¡P          not be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30 min

¡P          before and during odour patrol

4.2.13.    Odour patrol shall be conducted by independent trained personnel / competent persons patrolling and sniffing around the shore as shown in Figure 4.1 to detect any odour at the concerned hours (afternoon is preferred for higher daily temperature).

4.2.14.    The qualified person will use the nose (olfactory sensor) to sniff odours at different locations. The main odour emission sources and the areas to be affected by the odour nuisance will be identified.

4.2.15.    The perceived odour intensity is to be divided into 5 levels which are ranked in the descending order as follows:

¡P          0 - Not detected. No odour perceived or an odour so weak that it cannot be easily characterized or described;

¡P          1 - Slight Identifiable odour, and slight chance to have odour nuisance;

¡P          2 - Moderate Identifiable odour, and moderate chance to have odour nuisance;

¡P          3 - Strong Identifiable, likely to have odour nuisance;

¡P          4 - Extreme Severe odour, and unacceptable odour level.

 

4.2.16.    The findings including odour intensity, odour nature and possible odour sources, and also the local wind speed and direction at each location will be recorded. In addition, some relevant meteorological and tidal data such as daily average temperature, and daily average humidity, on that surveyed day will be obtained from the Hong Kong Observatory Station for reference. The Action and Limit levels for odour patrol are shown in Appendix 6.1.

4.2.17.    The qualified odour patrol member has individual n-butanol thresholds complied with the requirement of European Standard Method of Air Quality ¡V Determination of Odour Concentration by Dynamic Olfactometry (EN13725) in the range of 20 to 80 ppb.

4.3               Water Quality Monitoring

4.3.1.        The EIA Report has identified that the key water quality impact would be associated with the dredging works during the construction phase. Marine water quality monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is therefore recommended to be carried out at selected WSD flushing water intakes. The impact monitoring should be carried out during the proposed dredging works to ensure the compliance with the water quality standards.

4.3.2.        The updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by EPD on 29 April 2011. As such, the Action Level and Limit Level for the wet season (April ¡V September) will be effected and applied to the water quality monitoring data from 30 April 2011.

Water Quality Monitoring Stations

4.3.3.        It is proposed to monitor the water quality at 9 WSD salt water intakes and 14 cooling water intakes along the seafront of the Victoria Harbour. The proposed water quality monitoring stations of the Project are shown in Table 4.4 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.4      Marine Water Quality Stations for Water Quality Monitoring

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD7

Kowloon South

834150.0

818300.3

WSD9

Tai Wan

837921.0

818330.0

WSD10

Cha Kwo Ling

841900.9

817700.1

WSD15

Sai Wan Ho

841110.4

816450.1

WSD17

Quarry Bay

839790.3

817032.2

WSD19

Sheung Wan

833415.0

816771.0

WSD20

Kennedy Town

830750.6

816030.3

WSD21

Wan Chai

836220.8

815940.1

RW1

Wan Chai (Reprovision)

836188.8

815911.1

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

C2

Telecom House

835647.9

815864.4

C3

HKCEC Phase I

835836.2

815910.0

C4e

Great Eagle Centre

835932.8

815888.2

C4w

Wan Chai Tower

835629.8

815889.2

C5e

Sun Hung Kai Centre (Eastern)

836250.1

815932.2

C5w

Sun Hung Kai Centre (Western)

836248.1

815933.2

C6

Excelsior Hotel

837009.6

815999.3

C7

Windsor House

837193.7

816150.0

C8

City Garden

837970.6

816957.3

C9

Provident Garden

838355.0

817116.6

RC1

Proposed HKAPA Extension

835487.7

815987.7

RC5

Sun Hung Kai Centre (Reprovision)

836291.4

816029.7

RC7

Windsor House (Temporary Dilution)

837245.2

816156.6

 

Water Quality Parameters

4.3.4.        Monitoring of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried out at WSD flushing water intakes and cooling water intakes. DO and Turbidity are measured in-situ while SS is determined in laboratory.

4.3.5.        In association with the water quality parameters, other relevant data shall also be measured, such as monitoring location/position, time, sampling depth, water temperature, pH, salinity, dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal stage, and any special phenomena and work underway at the construction site etc.

Sampling Procedures and Monitoring Equipment

4.3.6.        The interval between two sets of monitoring should not be less than 36 hours except where there are exceedances of Action and/or Limit Levels, in which case the monitoring frequency will be increased. Table 4.5 shows the proposed monitoring frequency and water quality parameters. Duplicate in-situ measurements and water sampling should be carried out in each sampling event. For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

Table 4.5 Marine Water Quality Monitoring Frequency and Parameters

Activities

Monitoring Frequency1

Parameters2

During the 4-week baseline monitoring period

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

During marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

After completion of marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

Notes:

1.       For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

2.       Turbidity should be measured in situ whereas SS should be determined by laboratory.

Dissolved Oxygen and Temperature Measuring Equipment

4.3.7.        The instrument should be a portable, weatherproof dissolved oxygen measuring instrument complete with cable, sensor, comprehensive operation manuals, and use a DC power source. It should be capable of measuring:

¡P          a dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation

¡P          a temperature of 0-45 degree Celsius

4.3.8.        It should have a membrane electrode with automatic temperature compensation complete with a cable. Sufficient stocks of spare electrodes and cables should be available for replacement where necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).

4.3.9.        Should salinity compensation not be build-in in the DO equipment, in-situ salinity shall be measured to calibrate the DO equipment prior to each DO measurement.

Turbidity Measurement Instrument

4.3.10.    The instrument should be a portable, weatherproof turbidity-measuring instrument complete with comprehensive operation manual. The equipment should use a DC power source. It should have a photoelectric sensor capable of measuring turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model 2100P or an approved similar instrument).

Sampler

4.3.11.    A water sampler comprises a transparent PVC cylinder, with a capacity of not less than 2 litres, and can be effectively sealed with latex cups at both ends. The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (e.g. Kahlsico Water Sampler or an approved similar instrument).

Sample Container and Storage

4.3.12.    Water samples for suspended solids measurement should be collected in high-density polythene bottles, packed in ice (cooled to 4¢XC without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection for analysis.

Water Depth Detector

4.3.13.    A portable, battery-operated echo sounder shall be used for the determination of water depth at each designated monitoring station. This unit can either be handheld or affixed to the bottom of the workboat, if the same vessel is to be used throughout the monitoring programme.

Salinity

4.3.14.    A portable salinometer capable of measuring salinity in the range of 0-40 ppt shall be provided for measuring salinity of the water at each of monitoring location.

Monitoring Position Equipment

4.3.15.    A hand-held or boat-fixed type digital Global Positioning System (GPS) with waypoint bearing indication or other equivalent instrument of similar accuracy shall be provided and used during monitoring to ensure the monitoring vessel is at the correct location before taking measurements.

Calibration of In-situ Instruments

4.3.16.    All in-situ monitoring instrument shall be checked, calibrated and certified by a laboratory accredited under HOKLAS or equivalent before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring. Responses of sensors and electrodes should be checked with certified standard solutions before each use. Wet bulb calibration for a DO meter shall be carried out before measurement at each monitoring location.

4.3.17.    For the on site calibration of field equipment by the ET, the BS 127:1993, "Guide to Field and on-site test methods for the analysis of waters" should be observed.

4.3.18.    Sufficient stocks of spare parts should be maintained for replacements when necessary. Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

4.3.19.    Current calibration certificates of equipments are presented in Appendix 4.2.

Laboratory Measurement / Analysis

4.3.20.    Analysis of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the monitoring stations for carrying out the laboratory SS determination. The SS determination work shall start within 24 hours after collection of the water samples. The SS determination shall follow APHA 19ed or equivalent methods subject to the approval of IEC and EPD.

Enhanced Water Quality Monitoring in the ex-Wan Chai Public Cargo

Working Area and the Causeway Bay Typhoon Shelter

4.3.21.    The enhanced water quality monitoring and audit programme is to avoid aggravation of odour nuisance from seawater arising from temporary reclamation in the ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.

4.3.22.    Dissolved oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when there is temporary reclamation in Causeway Bay Typhoon Shelter and at the south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working Area. The proposed water quality monitoring stations of the Project are shown in Table 4.6 and Figure 4.1.

Table 4.6      Marine Water Quality Stations for Enhanced Water Quality Monitoring

Station

Location

C6

Excelsior Hotel

C7

Windsor House

Ex-WPCWA-SW

South-western of the ex-Wan Chai Public Cargo Working Area

Ex-WPCWA-SE

South-eastern of the ex-Wan Chai Public Cargo Working Area

 

4.3.23.    The monitoring of dissolved oxygen are to be carried out 3 days per week, at mid-flood and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth may be omitted. If the water depth be equal to or less than 3m, only the mid-depth will be monitored).

Daily SS Monitoring and 24 hours Turbidity Monitoring System

4.3.24.    During dredging of the sediment at the south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of suspended solids and 24 hour monitoring of turbidity at the cooling water intakes (C6 and C7) shall be conducted.

4.3.25.    The 24 hours monitoring of turbidty at the cooling water intakes (C6 and C7) shall be established by setting up a continuous water quality monitoring station in front of the intakes during the dredging activities. The monitoring system include the turbidity sensor and data logger which is capable of data capturing at every 5 minutes. The data sahll be downloaded daily and compared with the Action and Limit level determined during the baseline water qualtiy monitoring at the cooling water intake locations.

Additional Dissovled oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW

4.3.26.    In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored.

4.3.27.    The proposed DO monitoring stations of the Project are shown in Table 4.7 and Figure 4.1.

Table 4.7      Marine Water Quality Stations for Additional DO Monitoring

Station

Easting

Northing

A

835468

815857

B

835572

815961

C

835659

816271

 

4.3.28.    The monitoring of dissolved oxygen are to be carried out once per week, at mid-flood and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth may be omitted. If the water depth be equal to or less than 3m, only the mid-depth will be monitored).  

 

 

5.         Monitoring Results

5.0.1.        The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are presented in according to the Individual Contract(s).

5.0.2.        The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011.

5.0.3.        The surrender of the Further Environmental Permit for HY/2009/11 withdrew by contractor on 14 February 2012. However, there is no work was conducted by the contractor. 

5.0.4.        In the reporting month, the concurrent contracts are as follows:

Ÿ         Contract no. HY/2009/11 Central - Wan Chai Bypass - North Point Reclamation;

Ÿ         Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central-Wan Chai Bypass at Hong Kong Convention and Exhibition Centre; and

Ÿ         Contract no. HK/2009/02 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass at Wan Chai East

Ÿ         Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

Ÿ         Contract no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR Tsuen Wan Line

Ÿ         Contract no. HY/2009/19- Cental- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

5.0.5.        The environment monitoring schedules for reporting month and coming month are presented in Appendix 5.1.

5.1               Noise Monitoring Results

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

5.1.1.        The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011 and the FEP-01/356/2009 was under application of surrender in this reporting period. The monitoring was temporary suspended since 5 January 2012.

5.1.2.        The proposed division of noise monitoring stations for Contract no. HY/2009/11 are summarized in Table 5.1 below:

Table 5.1      Noise Monitoring Stations for Contract no. HY/2009/11

Station

Description

M4b

Victoria Centre

M5b

City Garden

5.1.3.        Day time and evening period noise monitoring was conducted at the City Garden and Victoria Centre in the reporting month.

5.1.4.        Noise monitoring results measured in this reporting period are reviewed and summarized. No exceedance was recorded in reporting month. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East and Contract no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR Tsuen Wan Line

5.1.5.        The proposed division of noise monitoring stations are summarized in Table 5.2 below.

Table 5.2      Noise Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06

Station

Description

M1a

Harbour Road Sports Centre

 

5.1.6.        Daytime and evening period noise monitoring was conducted at the Harbour Road Sport Centre in the reporting month.

5.1.7.        No exceedance was recorded in this reporting period. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.1.8.        The noise monitoring for HY/2009/15 was commenced on 10 November 2010. The proposed division of noise monitoring stations are summarized in Table 5.3 below.

Table 5.3      Noise Monitoring Station for Contract no. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

 

5.1.9.        Noise monitoring results measured in the period of daytime and restricted hour are reviewed and summarized. No exceedance was recorded in this reporting period. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2

Contract no. HY/2009/19- Wan Chai Bypass Tunnal (North Point Section) and Island Eastern Corridor Link

5.1.10.    The proposed division of noise monitoring stations are summarized in Table 5.4 below.

Table 5.4      Noise Monitoring Station for Contract no. HY/2009/19

Station

Description

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

 

 

 

 

 

5.1.11.    One limit level exceedance was recorded at M6 on 16 October 2012 in this reporting month. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2

5.2               Real-time Noise Monitoring

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation and Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

5.2.1          The real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of noise sensitive receiver- City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.

5.2.2          The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011 and the FEP-01/356/2009 was under application of surrender in this reporting period.

5.2.3          Exceedances were recorded between 2100 and 2130 hours on 1 Oct 2012 at FEHD Hong Kong Transport Section Whitefield Depot and Oil Street Community Centre throughout the reporting month.  Investigations found that the major noise impacts from 2100 to 2130 hours were arising from the display of pyrotechnics on 1 Oct 2012. In addition, there was no construction activity commenced in these two periods.  As such, the exceedances were concluded as not project related.

5.2.4          Real-time noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot commenced external wall renovation since 1 June 2012

Table 5.5 Real Time Noise Monitoring Station for Contract no. HY/2009/11 and HY/2009/19

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitefield Depot

North Point

RTN2

Oil Street Community Liaison Centre

North Point

RTN2a

Electric Centre

l             Real time noise monitoring results and graphical presentation during night time period are for information only.

l             RTN2 had been relocated to RTN2a since 5 Oct 2012

5.2.5          Details of real time noise monitoring results and graphical presentation can be referred to Appendix 5.5.

5.3               Air Monitoring Results

5.3.1.        Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b ¡V Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.

5.3.2.        Due to lack of electricity supply, the 24-hr TSP monitoring at the following stations were rescheduled:

CMA2a: from 22 October 2012 to 24 October 2012

CMA4a: from 29 September 2012 to 3 October 2012

 

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

5.3.3.        The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011and the FEP-01/356/2009 was valid in this reporting period. The monitoring for the contract was temporary suspended on 6 January 2012.

5.3.4.        The proposed division air monitoring stations is summarized in Table 5.6 below.

Table 5.6      Air Monitoring Stations for Contract no. HY/2009/11

Station

Description

CMA1b

Oil Street Community Liaison Centre

CMA2a

Causeway Bay Community Centre

5.3.5.        No exceedance was recorded in the reporting month. Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

5.3.6.        Air monitoring was commenced on 1 April 2011 in response to the commencement of the land-filling work for Contract no. HK/2009/01. The proposed divisions of air monitoring stations are summarized in Table 5.7 below. No exceedance was recorded in the reporting month.

Table 5.7      Air Monitoring Stations for Contract no. HK/2009/01

Station

Description

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

CMA6a

WDII PRE Site Office

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

5.3.7.        Air monitoring was commenced in mid-January 2011 for the land-filling work for Contract no. HK/2009/02. The proposed division of air monitoring stations are summarized in Table 5.8 below. No exceedance was recorded in the reporting month.

 

 

Table 5.8      Air Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.3.8.        Air monitoring was commenced on 15 March 2011 for the land filling work for Contract no. HY/2009/15. The proposed division of air monitoring stations are summarized in Table 5.9 below. No exceedance was recorded in the reporting month.

Table 5.9      Air Monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB PRE Site Office

 

Contract no. HY/2009/19- Wan Chai Bypass Tunnal (North Point Section) and Island Eastern Corridor Link

5.3.9.        The proposed division of air monitoring stations are summarized in Table 5.10 below. No exceedance was recorded in the reporting month.

Table 5.10 Air Monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Oil St Community Liaison Centre

CMA2a

Causeway Bay Community Centre

5.4               Water Monitoring Results.

5.4.1.        WDII/RSS advised that the dredging works for submarine pipeline at Victoria Harbour had been completed in January 2012. Therefore, the concurrent dredging activities at Sewage Pipeline Zone and reclamation shoreline zone TCBR under the EP-356/2009 scenario 2B no longer exist. As such, with reference to Table 5.39 of the EIA Report for Wan Chai Development Phase II and Central-Wan Chai Bypass, the application of silt screen for cooling water intakes for Queensway Government Offices was suspended and the others remain unchanged.

5.4.2.        Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no water deterioration with respect to NPR was commenced since 7 Jan 2012 and it was completed on 6 February 2012.

5.4.3.        Water quality monitoring at WSD10 and WSD15 was temporary suspended while water quality monitoring at WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 12 onwards;

5.4.4.        Water quality monitoring at C8 and C9 have been implemented with respect to HY/2009/19 since the marine bore piling work started on 28 Jan 12.

5.4.5.        Based on the safety concern when external façade refurbishment was conducted by contractor employed by Provident Centre (C9) since 3 Feb 2012, there is a fine adjustment of the sampling location of water quality monitoring at C9 to the closest accessible point prior to the completion of the external façade refurbishment work.

5.4.6.        With respect to the trial dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3 , 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21 during this period was checked and indicated that there was no contribution due to the trial dredging operation.  Enhanced review of water quality around WCR2 was also implemented and no deterioration in the water quality was observed.

5.4.7.        Due to the access of water monitoring station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and marine, there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012 to the closest accessible point prior to the completion of the construction activities.

5.4.8.        Due to the dredging works for Cross Harbour Water Mains from Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April 2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for 4-week period after the completion of DP6 to confirm no water deterioration.

 

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

5.4.9.        The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011 and the FEP-01/356/2009 was valid in this reporting period.

5.4.10.    The proposed division of water monitoring stations for Contract no. HY/2009/11 are summarized in Table 5.11 below:

Table 5.11    Water Monitoring Stations for Contract no. HY/2009/11

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD9

Tai Wan

837921.0

818330.0

WSD10

Cha Kwo Ling

841900.9

817700.1

WSD15

Sai Wan Ho

841110.4

816450.1

WSD17

Quarry Bay

839790.3

817032.2

Cooling Water Intake

C8

City Garden

837970.6

816957.3

C9

Provident Garden

838355.0

817116.6

      Remarks: WSD9, WSD10, WSD15, WSD17, C8 and C9 water monitoring finished on 6 Feb 2012.

 

 

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

5.4.11.    Water monitoring for Contract no. HK/2009/01 was commenced on 23 July 2010. The proposed division of water monitoring stations are summarized in Table 5.12 below.

Table 5.12    Water Monitoring Stations for Contract no. HK/2009/01

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD7

Kowloon South

834150.0

818300.3

WSD19

Sheung Wan

833415.0

816771.0

WSD20

Kennedy Town

830750.6

816030.3

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

C2

Telecom House

835647.9

815864.4

C3

HKCEC Phase I

835836.2

815910.0

C4e

Great Eagle Centre

835932.8

815888.2

C4w

Wan Chai Tower

835629.8

815889.2

Remarks:

- The water monitoring stations for the dredging works under Contract No. HK/2009/01 should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these locations have not been carried out by others. Similarly, the water monitoring stations for the dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations have not been carried out by others.

      - WSD7 and WSD20 water quality monitoring were temporarily suspended since 27 Apr 2012.

 

Contract no. HK/2009/02 - Wan Chai Development Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

5.4.12.    Water monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010. The proposed division of water monitoring stations are summarized in Table 5.13 below.

Table 5.13    Water Monitoring Stations for Contract no. HK/2009/02

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD21

Wan Chai

836220.8

815940.1

WSD9

Tai Wan

837921.0

818330.0

WSD17

Quarry Bay

839790.3

817032.2

Cooling Water Intake

C5e

Sun Hung Kai Centre (Eastern)

836250.1

815932.2

C5w

Sun Hung Kai Centre (Western)

836248.1

815933.2

Remarks:

-          The water monitoring stations for the dredging works under Contract No. HK/2009/01 should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these locations have not been carried out by others. Similarly, the water monitoring stations for the dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations has not been carried out by others.

-          Water quality monitoring at WSD9 and WSD 17 was implemented with respect to HK/2009/02 from 8 Feb 2012.

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line

5.4.13.    Water monitoring for Contract no. HK/2010/06 was commenced on 8 March 2011. The proposed division of water monitoring stations are summarized in Table 5.14 below.

Table 5.14    Water Monitoring Stations for Contract no. HK/2010/06

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C2

Telecom House

835647.9

815864.4

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.4.14.    As the removal of reclamation work of TS1 at CBTS has been completed, all procedures have been rectified and complied with the conditions set in EP-356/2009 and FEP-04/356/2009.

5.4.15.    Due to the commencement of the maintenance dredging on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was commenced on 9 November 2010. The proposed division of water monitoring stations are summarized in Table 5.15 below.

Table 5.15    Water Monitoring Stations for Contract no. HY/2009/15

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C6

Excelsior Hotel

837009.6

815999.3

C7

Windsor House

837193.7

816150.0

Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

 

Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

5.4.16.    Due to the commencement of the marine bored piling on 28 Jan 2012, water quality monitoring for Contract no. HY/2009/19 was commenced on 28 Jan 2012. The proposed division of water monitoring stations are summarized in Table 5.16 below.

Table 5.16    Water Monitoring Stations for Contract no. HY/2009/19

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C8

City Garden

837970.6

816957.3

C9

Provident Garden

838355.0

817116.6

        Remarks: C8 and C9 monitoring commenced on 28 Jan 2012.

5.4.17.    Based on the safety concern when external façade refurbishment was conducted by contractor employed by Provident Center (C9) between 9 January 2012 to 30 July 2012 which caused to the inaccessibility of sampling either land and marine since 3 Feb 2012, there is a fine adjustment of the sampling location of water quality monitoring at C9 since 10 March 2012 to the closest accessible point prior to the completion of the external façade refurbishment work.

5.4.18.    Due to the access of water monitoring station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and marine, there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012 to the closest accessible point prior to the completion of the construction activities.

5.4.19.    As per the meeting with the representative of Excelsior Hotel and World Trade Centre on 17 May 2011, they confirmed that the seawater intake for The Excelsior was no longer in use and replaced by the connected permanent water supply from WSD pipelines since 11 January 2011. Thus, the impact water quality monitoring for the cooling intake - C6 was terminated effective from 26 May 2011.

5.4.20.    24 hours monitoring of turbidity at the cooling water intakes at C7 was conducted. With respect to the seawall collapsing at TS4 on 17 November 2011, the 24 hours turbidity monitoring and was kept in November 2011. Since the reinstating the seawall was completed on 13 January 2012 and no any water deterioration was performed, 24 hour turbidity monitoring was then suspended on 27 January 2012.

5.4.21.    Water monitoring results measured in this reporting period are reviewed and summarized. Details of water quality monitoring results and graphical presentation can be referred in Appendix 5.4.

 

Table 5.17    Summary of Water Quality Monitoring Exceedances in Reporting Month

 

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HY/2009/11

WSD9

0

0

0

0

0

0

0

0

0

0

0

0

Monitoring finished on

6 Feb 2012

WSD10

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD15

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD17

0

0

0

0

0

0

0

0

0

0

0

0

 

C8

0

0

0

0

0

0

0

0

0

0

0

0

 

C9

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/01

WSD19

0

0

0

4

0

3

0

0

2

2

0

2

 

C1

1

0

0

0

0

0

0

0

0

0

0

0

 

C3

4

0

0

0

1

0

0

0

0

0

0

0

 

C4e

1

0

0

0

0

0

1

0

0

0

0

0

 

C4w

2

1

0

0

0

0

3

0

0

0

0

0

Monitoring finished on 27 April 2012

WSD20

0

0

0

0

0

0

0

0

0

0

0

0

WSD7

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/01

& HK/2010/06

C2

0

0

0

0

1

0

0

0

0

0

0

0

HK/2009/02

C5e

0

0

0

2

0

1

0

0

0

2

1

1

 

C5w

0

0

1

1

0

1

0

0

0

3

0

2

Monitoring started on

8 Feb 2012

WSD21

4

2

0

0

3

1

3

1

1

0

0

0

WSD9

0

0

0

0

1

0

0

0

0

0

0

0

 

WSD17

0

0

1

7

0

5

0

0

0

1

0

1

HY/2009/15

C7

1

1

0

0

0

0

2

0

0

0

0

0

HY/2009/19

Monitoring started on 28 Jan 2012

C8

0

0

3

4

1

0

0

0

1

1

0

0

C9

0

0

4

2

2

1

0

0

2

0

0

0

Total

13

4

9

20

9

12

9

1

6

9

1

6

 

Remarks: -    The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

         -   WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.

-   4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 were completed on 6 Feb 2012.

-   C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-   WSD7 and WSD20 were temporarily suspended from 27 Apr 2012

5.4.22.    Investigations were found that three turbidity and two SS project related exceedances recorded at C5e on 13, 15 and 25 Oct 2012. In addition, three turbidity and three SS project related exceedances were recorded at C5w on 13, 15 and 20 Oct 2012. The details of the recorded exceedances can be referred to the Section 6.4.

5.4.23.    Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table 5.18.

Table 5.18     Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

              

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

DO

AL

LL

AL

LL

HY/2009/15

C6

1

0

0

0

C7

3

2

1

1

Ex-WPCWA SW

1

8

1

9

Ex-WPCWA SE

4

6

3

7

Total

9

16

5

17

 

 

5.4.24.    There were 14 action level exceedances and 33 limit level exceedances recorded in enhanced dissolved oxygen monitoring in this reporting period.

5.4.25.    In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored. Details of additional DO monitoring results can be referred in Appendix 5.4a.

 

5.5               Waste Monitoring Results

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

5.5.1.        The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. Therefore, no C&D waste was generated.

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

5.5.2.        No Inert C&D waste was disposed and non- inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.19.

Table 5.19     Details of Waste Disposal for Contract no. HK/2009/01

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

0

22245.415

TKO137, TM38

Inert C&D materials recycled, m3

105

5104.5

N/A

Non-inert C&D materials disposed, m3

32.76

1049.7

SENT Landfill

Non-inert C&D materials recycled, kg

0

151143

N/A

Chemical waste disposed, kg

250

8050

N/A

*Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

0

(Bulk Volume)

91164.2

(Bulk Volume)

South of Cheung Chau

* Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

767

(Bulk Volume)

43785

(Bulk Volume)

East of Cha Chau

 

Dredged Sediment Requiring Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers

 

1160

 (Bulk Volume)

 

6773

(Bulk Volume)

 

East of Cha Chau

5.5.3.        There were no marine sediments Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal disposed in the reporting month.

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

5.5.4.        Inert and non- inert C&D waste were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.20.

Table 5.20     Details of Waste Disposal for Contract no. HK/2009/02

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

12932.4

213739.4

TKO137 / TM 38

Inert C&D materials recycled, m3

NIL

18161

N/A

Non-inert C&D materials disposed, m3

40

649

SENT Landfill

Non-inert C&D materials recycled, m3

NIL

NIL

N/A

Chemical waste disposed, kg

0

5521

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

NIL

154,827

(Bulk volume)

South of Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

Nil

114464

(Bulk volume)

East of Sha Chau

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.5.5.        No Inert C&D waste was disposed and non- inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.21

Table 5.21     Details of Waste Disposal for Contract no. HY/2009/15

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

141579.2

Tuen Mun Area 38

NIL

65216

TKO137 FB

Inert C&D materials recycled, m3

NIL

184.0

To Contract HY/2009/11

NIL

304

ex-PCWA

NIL

111.9

TS4

Non-inert C&D materials disposed, m3

NIL

252.2

SENT Landfill

Non-inert C&D materials recycled, kg

NIL

299361.5

N/A

Chemical waste disposed, kg

NIL

8,200

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

NIL

 

97,857

(Bulk Volume)

South of Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

NIL

207,285

(Bulk Volume)

East of Sha Chau

Marine Sediment (Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers)

NIL

7,050

(Bulk Volume)

East of Sha Chau

 

 

No Marine sediment (Type 1 ¡V Open Sea Disposal) was disposed of in this reporting month.

 

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line

5.5.6.        Non-inert C&D waste was disposed and Inert C&D waste was recycled in this reporting month. Details of the waste flow table are summarized in Table 5.22.

Table 5.22     Details of Waste Disposal for Contract no. HK/2010/06

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

0

11366.23

TM38

Inert C&D materials recycled, m3

45

311.8

N/A

Non-inert C&D materials disposed, m3

2.39

2.39

N/A

Non-inert C&D materials recycled, kg

0

1374.5

N/A

Chemical waste disposed, L

0

                 600

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

0

(Bulk Volume)

3,694

(Bulk Volume)

South Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

0 (Bulk Volume)

12,297

(Bulk Volume)

East Sha Chau

There were no marine sediments Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal dredging from bore-piling casing in the reporting month.

Contract no. HY/2009/19 ¡VCentral- WanChai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

5.5.7.        Inert and non-inert C&D waste were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.23.

Table 5.23 Details of Waste Disposal for Contract no. HY/2009/19

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

20134.29

75719.06

TM38

Inert C&D materials recycled, m3

1128

1128

N/A

Non-inert C&D materials disposed, m3

27.39

112.21

N/A

Non-inert C&D materials recycled, kg

104.64

104.64

N/A

Chemical waste disposed, L

NIL

0.29

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

0

83

South Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

0

482

East Sha Chau

There was no marine sediments Type1- Open Sea Disposal and Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal dredging from bore-piling casing in the reporting month.

6.         Compliance Audit

6.0.1.        The Event Action Plan for construction noise, air quality and water quality are presented in Appendix 6.1.

 

6.1               Noise Monitoring

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

6.1.1          No exceedance was recorded in the reporting month.

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

6.1.2          No exceedance was recorded in the reporting month.

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East 

6.1.3          No exceedance was recorded in the reporting month.

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

6.1.4          No exceedance was recorded in the reporting month.

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line

6.1.5          No exceedance was recorded in the reporting month.

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

6.1.6          One limit level exceedances were recorded at M6 ¡V HK Baptist Church Henrietta Secondary School on 16 October 2012 in the reporting month.  Investigations found that major traffic noise was contributed in the noise monitoring and not related to the Project.

6.2               Real-time noise Monitoring

6.2.1          Exceedances were recorded between 2100 and 2130 hours on 1 Oct 2012 at FEHD Hong Kong Transport Section Whitefield Depot and Oil Street Community Centre throughout the reporting month.  Investigations found that the major noise impacts from 2100 to 2130 hours were arising from the display of pyrotechnics on 1 Oct 2012. In addition, there was no construction activity commenced in these two periods.  As such, the exceedances were concluded as not project related.

6.3               Air Monitoring

6.3.1.        No exceedance was recorded in 1-hr TSP and 24-hrs TSP monitoring in the reporting month.

6.4               Water Quality Monitoring

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

6.4.1          No exceedance was recorded in the reporting month.

 

 

 

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

6.4.2          There were occasionally DO exceedances recorded at C1, C3, C4e and C4w in this reporting month. No odour nuisance was noted during DO monitoring. Confirmed with Contractor, there was no work conducted during the water quality monitoring. The exceedances were possible in relation to the natural variation or changes of water quality in the vicinity of the water quality monitoring station and not project related.

6.4.3          Turbidity and SS exceedances at WSD19 were occasionally recorded in this reporting month. In view that the water quality at monitoring stations located nearest the marine work site were well below Action Level and the silt screen was in proper condition, the exceedances were possible in relation to the changes of water quality in the vicinity of the water quality monitoring station and not project related.

6.4.4          SS exceedance at C2 was recorded on 25 October 2012. According to the information reported by Contractor HK/2010/06 and HK/2009/01 on 25 Oct 2012, pile head breaking under HK/2010/06 and filling at HKCEC water channel under HK/2009/01 were conducted on that day. In view that the water quality at monitoring stations located nearest the marine work site were well below Action Level and the silt screen was in proper condition, the exceedance was possible in relation to the natural variation or changes of water quality in the vicinity of the water quality monitoring station and not project related.

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East 

 

6.4.5          There were turbidity and SS exceedances recorded at C5w on 8 Oct 2012 during ebb tide. Checking with Contractor¡¦s work, no marine work was conducted on that day. Checking with contractor's inspection record, the silt screen was in proper condition on that day. The exceedance was considered as trapping of unknown particles inside the silt screen. The contractor was reminded water quality near to the intake should be provided with sufficient protection. The exceedance was considered not project related.

6.4.6          There were turbidity and SS exceedances recorded at C5e and C5w on 13 and 15 Oct 2012 during ebb tide. Muddy water quality appearance inside and outside silt screen were observed during monitoring. Checking with Contractor¡¦s work, rockfilling near temporary seawall at WCR2 was conducted on that day. Checking with contractor's inspection record, the silt screen and silt curtain for rockfilling were in proper condition on that day. Although the Contractor's records have shown a well maintained silt curtain and silt screen, muddy water was still observed around the intake during monitoring.  The turbidity and SS concentration has returned to below the Action Level after stopping of filling works during the flood tide.  This shows possible defects at the silt curtain and that protection around the intake is inadequate to protect the sensitive receiver during the filling activities.

6.4.7          There were turbidity exceedances recorded at C5e and C5w on 17 Oct 2012 during flood tide. Checking with Contractor¡¦s work, rockfilling in WCR2 was conducted on that day. Checking with contractor's inspection record, the silt screen and silt curtain for rockfilling were in proper condition on that day. The exceedance was considered as natural variation or changes of water quality in the vicinity of the water quality monitoring station and not project related.

6.4.8          There were turbidity and SS exceedances recorded at C5w on 20 October 2012 during flood tide. Silty water was observed discharging from water pipe into Well B during monitoring. 21.65 NTU turbidity was recorded outside the silt screen. Contractor immediately removed the pipe from Well B. ET reminded Contractor should ensure the water pumping into Well for cooling purpose should not deteriorate the water quality of intake. No further exceedance was recorded in the next consecutive water monitoring on 22 Oct. The turbidity and SS concentration has returned to below the Action Level after removal of water pipe.

6.4.9          There were turbidity and SS exceedances recorded at C5e on 25 October 2012 during flood tide. Muddy dispersion into the Well as a result of the rockfilling in WCR2 was observed during inspection walk on 25 Oct. ET recommended that gaps at temporary sheet pile at Well B should be sealed up and the turbid water inside well should be treated to improve the water quality in the well. Daily water quality monitoring at C5e was conducted on 26 Oct 12 under Event and Action Plan. The turbidity of C5e was 7.38 NTU on 26 Oct 12 which is below Action level. The turbidity and SS concentration has returned to below the Action Level after the improvement of condition of temporary sheet pile at Well.

6.4.10      There were occasionally DO, turbidity and SS exceedances recorded at WSD21 in this reporting month. Checking with Contractor¡¦s work, rockfilling in WCR2 was conducted on those days. Checking with contractor's inspection record, the silt screen and silt curtain for rockfilling were in proper condition on that day. The exceedance was considered as natural variation or changes of water quality in the vicinity of the water quality monitoring station and not project related.

6.4.11      There was SS exceedance at mid-flood recorded at WSD21 on 15 October 2012. Confirmed with Contractor, Checking with Contractor¡¦s work, rockfilling in WCR2 was conducted on those days. Checking with contractor's inspection record, the silt screen and silt curtain for rockfilling were in proper condition on that day. The exceedance was possibly due to cleaning of screen panels at WSD intake. Materials from the cleaning of screen panels were unavoidably collected during monitoring. The exceedance was considered as not project related.

6.4.12      There were DO exceedances recorded at WSD21 on 4, 6 and 10 October 2012 in this reporting month. No odour nuisance was noted during DO monitoring. Confirmed with Contractor, there was no work conducted during the water quality monitoring. The exceedance was considered as natural variation or changes of water quality in the vicinity of the water quality monitoring station and not project related.

6.4.13      There were occasionally turbidity and SS exceedances recorded at WSD17 and WSD9 in this reporting month. In view that the water quality at monitoring stations located nearest the marine work site were well below Action Level and the silt screen was in proper condition, the exceedance was possible in relation to the natural variation or changes of water quality in the vicinity of the water quality monitoring station and not project related.

6.4.14      There were turbidity and SS exceedances recorded at WSD17 on 28 September 2012 and 2 October 2012. Checking with contractor¡¦s record, cleaning screen panel at Quarry Bay WSD intake was conducted on these days. The exceedances were possibly due to cleaning of screen panels at the WSD intake. Material from the cleaning of screen panels was avoidably collected during monitoring. The exceedance was considered as not project related.

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

6.4.15      There were occasionally DO exceedances recorded at C6 and C7 in this reporting month. After checking with the Contractor¡¦s works, the deployed silt curtain was in proper condition for TS2 seawall construction. The exceedances were possible in relation to the natural variation or changes of water quality in the vicinity of the water quality monitoring station and not project related.

6.4.16      There were occasionally DO exceedances at Ex-WPCWA SE and Ex-WPCWA SW recorded in this reporting month. No odour nuisance was noted during DO monitoring. After checking with Contractor, there was no marine work undertaken at ex-WPCWA. The exceedances were possible in relation to the accumulation of organic particles discharge from culvert near monitoring station and considered not related to the Projects works.

 

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line

 

6.4.17      SS exceedance at C2 was recorded on 25 October 2012. According to the information reported by Contractor HK/2010/06 and HK/2009/01 on 25 Oct 2012, pile head breaking under HK/2010/06 and filling at HKCEC water channel under HK/2009/01 were conducted on that day. In view that the water quality at monitoring stations located nearest the marine work site were well below Action Level and the silt screen was in proper condition, the exceedance was possible in relation to the natural variation or changes of water quality in the vicinity of the water quality monitoring station and not project related.

 

Contract no. HY/2009/19- Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

6.4.18      There were occasionally turbidity and SS exceedances at C8 and C9 recorded in this reporting month. Confirmed with Contractor, there was no marine work conducted near C8 and C9.The exceedances were possible in relation to the accumulation of particles discharged from outfalls near monitoring stations and not related to project.

6.4.19      Summary for notification of exceedances can be referred to Appendix 6.2.

 

6.5               Review of the Reasons for and the Implications of Non-compliance

6.5.1          There was no non-compliance from the site audits in the reporting month. The observations and recommendations made in each individual site audit session were presented in Section 8.

 

6.6               Summary of action taken in the event of and follow-up on non-compliance

6.6.1          There was no particular action taken since no project-related non-compliance was recorded from the site audits and environmental monitoring in the reporting month.

7.         Cumulative Construction Impact due to the Concurrent Projects

7.0.1.        According to Condition 3.4 of the EP-356/2009, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.

7.0.2.        According to the Monthly EM&A report (September 2012) of Central Reclamation Phase III (CRIII), filling works, building construction works and pipe works were performed in the October 2012 reporting month. The water quality monitoring was completed in October 2011 and no exceedance was recorded for air and noise monitoring. It can be concluded that cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was insignificant.

7.0.3.        According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activities at Reclamation Shoreline Sub-zones under Wan Chai Development Phase II were the dredging and filling at HKCEC3w, dredging at submarine sewage pipelines, reinstatement of seawall block construction at TCBR1W and marine bored piling at MTR Tunnel Crossing in the reporting month. The major environmental impact was water quality impact at, Causeway Bay and Wan Chai.

7.0.4.        The major environmental impacts generated from the reclamation work at Central Reclamation Phase III were only located along the coastline of Central and Admiralty while the adverse water impact was only located in the WCR2 in relation to the rock filling operation causing exceedances in WCR2 in this reporting month. Thus, it was unlikely to have cumulative impact from CRIII. It is evaluated the cumulative construction impact from the concurrent projects including Wan Chai Development Phase II and Central Reclamation Phase III was insignificant.

8.         Environmental Site Audit

8.0.1.        During this reporting month, weekly environmental site audits were conducted for Contracts no.  HK/2009/01, HK/2009/02, HY/2009/15, HK/2010/06 and HY/2009/19. No non-conformance was identified during the site audits.

8.0.2.        Four site inspections for Contract no. HK/2009/01 were carried out on 3, 10, 18 and 24 October 2012 in reporting month. Results of these inspections and outcomes are summarized in Table 8.1.

Table 8.1      Summary of Environmental Inspections for Contract no. HK/2009/01

Item

Date

Observations

Action taken by Contractor

Outcome

121003_01

3-Oct-12

The oil stain was observed on the ground which should be removed and disposed as chemical waste. (VIP area)

The oil stain was removed

Completion as observed on 10-Oct-12

 

121010_01

10-Oct-12

Drip tray should be provided for oil drums (Grand Hyatt)

The oil drums were removed.

Completion as observed on 18-Oct-12

121010_02

10-Oct-12

Existing trees to be retained on site shall be carefully protected during construction (Pumping station, C1 site office)

The construction materials were removed

Completion as observed on 18-Oct-12

121018_01

18-Oct-12

The oil leakage from the drilling machine was observed.  The contractor should provide better maintenance of machine and removed the oil stain as chemical waste (Expo East Bridge)

The oil stain was removed.

Completion as observed on 24-Oct-12

121024_01

24-Oct-12

The oil stain was observed on ground which should be removed and disposed as chemical waste (Near to Grand Hyatt)

The oil stain was removed

Completion as observed on 31-Oct-12

 

8.0.3.        Four site inspections for Contract no. HK/2009/02 were carried out on 4, 11, 17 and 25 October 2012 during this reporting period. The results of these inspections and outcomes are summarized in Table 8.2.

Table 8.2      Summary of Environmental Inspections for Contract no. HK/2009/02

Item

Date

Observations

Action taken by Contractor

Outcome

121004_02

4-Oct-12

Drip tray should be provided for oil drums (WCR1)

The oil drums were removed.

Completion as observed on 11-Oct-12

121011_01

11-Oct-12

Cares should be taken to prevent dust to be exposed on public road (WSD pumping station)

The dust in the road was removed.

Completion as observed on 17-Oct-12

121011_02

11-Oct-12

Existing trees to be retained should be carefully protected during construction (Opposite to WSD pumping station)

The existing trees were carefully protected.

Completion as observed on 17-Oct-12

121017_01

17-Oct-12

Measure should be taken to prevent mud and dusty materials from vehicles is deposited on roads
(Old gate 2, Ex-helipad)

The wheel washing facilities was provided in the exit of vehicular site.

Completion as observed on 25-Oct-12

121017_02

17-Oct-12

Dark smoke emission from generator was observed. The maintenance of generator should be provided to avoid dark smoke emission. (WCR1)

The generator was removed.

Completion as observed on 25-Oct-12

121017_03

17-Oct-12

Existing tree (T0031) to be retained on site should be protected during construction (Opposite to WSD pumping station)

The tree T0031 was protected during construction.

Completion as observed on 25-Oct-12

121025_01

25-Oct-12

The seepage of muddy water into Victoria Harbour from Eastern temporary seawall was observed. Measures should be taken to prevent the seepage of muddy water.(WCR1)

The silt curtain and geotextile were provided along the temporary seawall.

Completion as observed on 1-Nov-12

121025_02

25-Oct-12

Tree protection fence should be provided for retained tree during construction.(Opposite to WSD pumping station)

The tree protection fence was provided.

Completion as observed on 1-Nov-12

8.0.4.        Four site inspections for Contract no. HY/2009/15 were carried out on 3, 9, 16 and 24 October 2012 in reporting month. The results of these inspections and outcomes are summarized in Table 8.3.

Table 8.3      Summary of Environmental Inspections for Contract no. HY/2009/15

Item

Date

Observations

Action taken by Contractor

Outcome

121003_01

3-Oct-12

Chemical drums were observed to be without drip tray at several locations, the contractor should provide adequate measures and storage area for chemical drums. (TPCWAE, TS4)

Drip tray was provided for chemical drums.

Completion as observed on 9-Oct-12

 

121009_01

9-Oct-12

The oil leakage was observed on ground which should be cleaned and removed as chemical waste(TS1 and TS4)

The oil stain was removed as chemical waste.

Completion as observed on 16-Oct-12

121009_02

9-Oct-12

Cares should be taken to prevent the mud trail occur on the public road (Gate of TS4, outside POC)

the muddy trail was removed.

Completion as observed on 16-Oct-12

121009_03

9-Oct-12

Muddy water was observed around the public gully, preventive action should be provided to avoid the illegal discharge. (Gate of TS4, outside POC)

The muddy water was removed.

Completion as observed on 16-Oct-12

121016_01

16-Oct-12

Three sides and top cover enclosure should be provided for grouting work (TS4, TPCWAE)

Better cover was provided for grouting plants.

Completion as observed on 24-Oct-12

121016_02

16-Oct-12

The condition of silt curtain should be improved (northern TPCWAE)

Additional silt curtain was provided at the concerned area.

Completion as observed on 24-Oct-12

121016_03

16-Oct-12

Drip tray shall be proivded for chemical containers and holes should be plugged to avoid leakage. (TPCWAE, TS4)

Drip trays were provided for chemical drums.

Completion as observed on 24-Oct-12

121016_04

16-Oct-12

Ventilation at grouting plants should be improved to avoid dust generation outside covered area. (TS4, near nothern treatment plant)

Ventilation pipes were maintained to avoid gaps and holes.

Completion as observed on 24-Oct-12

121024_01

24-Oct-12

Proper cover and filtration system for grouting facilities to ensure proper dust control. (TS4, TPCWAE)

Proper cover placed to enclose grouting and filtration system

Completion as observed on 30 Oct-12

121024_02

24-Oct-12

Proper storage facilities and drip trays should be provided for chemicals and oil drums (Eastern Breakwater, TS4)

Chemicals and oil drums were removed from the previous location to other proper storage

Completion as observed on 30 Oct-12

 

8.0.5.        Four site inspections for Contract no. HK/2010/06 was carried out on 3, 8, 18 and 22 October 2012 in reporting month. The results of these inspections and outcomes are summarized in Table 8.4.

Table 8.4      Summary of Environmental Inspections for Contract no. HK/2010/06

Item

Date

Observations

Action taken by Contractor

Outcome

121003_01

3-Oct-12

The oil stain was observed on the ground which should be removed and disposed as chemical waste.(2w)

The oil stain was removed as chemical waste.

Completion as observed on 8-Oct-12

121018_01

18-Oct-12

The silt accumulated in u-channel should be cleaned more regularly (2e)

 

The silt accumulated in U-channel was cleaned.

Completion as observed on 18-Oct-12

 

 

 

 

 

 

 

 

8.0.6.        Four site inspections for Contract no. HY/2009/19 were carried out on 3, 10, 17 and 24 October 2012 in reporting month. The results of these inspections and outcomes are summarized in Table 8.5.

Table 8.5   Summary of Environmental Inspections for Contract no. HY/2009/19

Item

Date

Observations

Action taken by Contractor

Outcome

121010_01

10-Oct-12

Oil leakage should be cleared as chemical waste, oil drums should be stored at appropriate storage area.  (Portion III by Oil Street Exit)

Oil leakage and oil drums were removed.

Completion as observed on 17-Oct-12

121017_01

17-Oct-12

Drip tray should be provided for generator (Portion VI)

Drip tray was provided for generator.

Completion as observed on 24-Oct-12

9. Complaints, Notification of Summons and Prosecution

9.0.1.        There was no complaint received in this reporting month.

9.0.2.        The details of cumulative complaint log and updated summary of complaints are presented in Appendix 9.1.

9.0.3.        Cumulative statistic on complaints and successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.

Table 9.1 Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

Commencement works (Mar 2010) to last reporting month

27

October 2012

0

Project-to-Date

27

 

Table 9.2 Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

 

10.        Conclusion

10.0.1.    The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

10.0.2.    WDII/RSS advised that the dredging works for submarine pipeline at Victoria Harbour had been completed in January 2012. Therefore, the concurrent dredging activities at Sewage Pipeline Zone and reclamation shoreline zone TCBR under the EP-356/2009 scenario 2B no longer exist. As such, with reference to Table 5.39 of the EIA Report for Wan Chai Development Phase II and Central-Wan Chai Bypass, the application of silt screen for cooling water intakes for Queensway Government Offices was suspended and the others were remains unchanged.

10.0.3.    The real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of noise sensitive receiver- City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.

10.0.4.    Water quality monitoring at WSD10 and WSD15 will be temporary suspended while water quality monitoring at WSD9 and WSD17 were implemented with respect to HK/2009/02 for the water quality monitoring scheduled on 8 Feb 12 onwards;

10.0.5.    Water quality monitoring at C8 and C9 have been implemented with respect to HY/2009/19  since the marine bore piling work started on 28 January 2012.

10.0.6.    Based on the safety concern when external façade refurbishment was conducted by contractor employed by Provident Centre (C9) between 9 January 2012 to 30 July 2012 which caused to the inaccessibility of sampling either land and marine since 3 Feb 2012, there is a fine adjustment of the sampling location of water quality monitoring at C9 since 10 March 2012 to the closest accessible point prior to the completion of the external façade refurbishment work.

10.0.7.    Due to the access of water monitoring station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and marine, there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012 to the closest accessible point prior to the completion of the construction activities.

10.0.8.    With respect to the trial dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3, 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21 during this period was checked and indicated that there was no contribution due to the trial dredging operation.  Enhanced review of water quality around WCR2 was also implemented and no deterioration in the water quality was observed.

10.0.9.    Due to the dredging works for Cross Harbour Water Mains from Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April 2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for 4-week period after the completion of DP6 to confirm no water deterioration.

10.0.10. The scheduled construction activities and the recommended mitigation measures for the coming month are listed in Table 10.1.

Table 10.1     Construction Activities and Recommended Mitigation Measures in Coming Reporting Month

Contract No.

Key Construction Works

Recommended Mitigation Measures

HK/2009/01

Marine Works

¡P         Fabrication of precast concrete caisson seawalls, precast box culvert (Bay 10) and precast discharge outfall in precasting yard at Guangdong, China and anticipated to be delivered to Site. Installation of the precast units

¡P         Dredging works for Type 2 sediment underneath Expo Drive East Bridge

¡P         Dredging works between CH290 and CH370 at east of HKCEC near Wan Chai west ferry pier

¡P         Grouting works and tie back system for construction of pipe pile wall near Expo Drive East. Removal of seawall at Expo Drive East

¡P         Rockfilling at east of HKCEC near Expo Drive East

¡P         Trust block construction at TST landfall

¡P         Rockfilling and rock armour protection works to cross-harbour watermains

¡P         Reinstatement works at TST seashore including removal of silt screen and demobilization of jack-up barge

¡P         Fresh water flushing, final cleaning and sterilizatioin for cross-harbour watermains CHA, CHB, CHE & CHF

¡P         Installation of Impressed Current Cathodic Protection (ICCP) system to CHA and CHB

 Fresh Watermains, Cooling Watermains and Salt Watermains (On Land)

¡P         Works would be continued at Zone B1-5A, B2-1, B5-1(Switch Room), B5- 3(Switch Room), A1-1, A1-2, A2-2, A1-4(CHWM), A2-3D, A3-2A, A3-4B, run-out of Renaissance Hotel and C1-10

¡P         Mainlaying works at Zone C1-10 and run-out of Renaissance Hotel

¡P         Reinstatement works at Zone B1-5A and B2-1

¡P         Mainlaying works at Zone B3-1

¡P         Mainlaying works at Convention Avenue in Zone A1-1 and A1-2 and the next TTA workfront at Zone A1-2 (CHWM)

¡P         Mainlaying works and grouting works at jacking pit in Zone A1-3A & A1-4A of Convention Avenue would be resumed upon completion of pressure test for intake and discharge pipeline of SOC and HKAPA.

¡P         Mainlaying works at traffic island near junction between Convention Avenue and Fenwick Pier Street

¡P         Pipe laying works for Heading no. H1

¡P         Mainlaying works at Zone A3-4B and the works at Zone A3-4A & A3-5A would be subsequently commenced concurrently after the Zone A3-4B had been completed reinstated and reopened to public.

¡P         Pipe laying works for cross harbour watermains across HKCEC water channel

¡P         Pressure test for the 9 nos. cooling watermains

E&M Works

¡P         Electrical works in Cooling Water Pumping Stations P5

¡P         Initial commissioning for Cooling Water Pumping Stations P5

¡P         Major cabling works from existing LV Switch-board Room to Cooling Water Pumping Stations P5

¡P         Power energization for Cooling Water Pumping Stations P5

¡P         Full commissioning for Cooling Water Pumping Stations P1

¡P         Full commissioning for Cooling Water Pumping Stations P3, P4 & P5

¡P         To conform the installation and setting as in the silt screen deployment plan

¡P         Frequency spray water on the dry dusty road and on the surface of concrete breaking

¡P         To cover the dusty material or stockpile by impervious sheet

¡P         To space out noisy equipment and position as far as possible from sensitive receiver.

¡P         To well maintain the mechanical equipments / machineries to avoid abnormal noise nuisance.

¡P         Machines and plant that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum

¡P         Daily visual inspection of silt screen and silt curtain to ensure its operation properly

HK/2009/02

¡P         Complete PTI modification works after completion of New Public Toilet in East Island at Expo Drive East.

¡P         Complete all cooling mains and cabling works for P7, P8 & P9 Pumping Stations permanent power-on and signal control.

¡P         Continue 800MS pipe installation inside Ex-pet Garden.

¡P         Complete modification work of EVA & Vehicle access at WSD Pumping Station

¡P         Complete the finishing works of WSD Salt Water Pumping Station.

¡P         Continue construction of Bay 1b ¡V 2, Bay 6 ¡V 8 salt water intake culverts at WCR1 area.

¡P         Complete ELS of the salt water intake culverts Bay 9 ¡V 11 to formation level at WCR1 area and commence culvert works.

¡P         Continue salt water intake culvert at transition bays inside jacking pit and receiving pit.

¡P         Continue remaining drainage works and reinstatement works along Wan Shing Street.

¡P         Complete HDPE piping inside outfall seaside cofferdam.

¡P         Continue construction for Box Culvert N1 at WCR1 area.

¡P         Continue concreting works for the Mezzanine Level at the New Ferry Pier.

¡P         Commence seawall strengthening works at WCR2 area.

¡P         .

¡P         To cover the dusty material or stockpile by impervious sheet;

¡P         Frequency spray water on the dry dusty road and on the surface of concrete breaking

¡P         To well maintain the mechanical equipments / machineries to avoid abnormal noise nuisance and dark smoke emission

¡P         To conform the installation and setting as in the silt screen and silt curtain deployment plan

¡P         Movable noise barrier shall be deployed for demolition works

¡P         Daily visual inspection of silt screen and silt curtain to ensure its operation properly

¡P         Review silt screen deployment and silt curtain deployment and resubmit associate plans to EPD

¡P         Implement silt screen and silt curtain in accordance with the associated plans submitted to EPD.

 

HY/2009/15

¡P         Formation of temporary seawall at TS2

¡P         TZ1 and TS2 reclamation works

 

¡P         Watering any dust generating activities

¡P         Checking all drip trays frequently and clear any stagnant water and mud inside it.

¡P         Noise control measures shall be provided during restricted hours.

 

HK/2010/06

¡P         Pile head breaking

¡P         Platform Disassembly

¡P         Sonic tube trimming

¡P         Dredging

 

 

 

¡P         To conform the installation and setting as in the silt screen and silt curtain deployment plan

¡P         To space out noisy equipment and position as far as possible from sensitive receiver.

¡P         Daily visual inspection of silt screen and silt curtain to ensure its operation properly

HY/2009/19

¡P         Construction works for Box Culvert T

¡P         Marine Piling

¡P         Construction of 1500f drainage pipe

¡P         To conform the installation and setting as in the silt screen and silt curtain deployment plan